Agilent Technologies varian 320-MS LC/MS Pre-Installation Instructions Download Page 13

9300025700: Rev. A 

13

 

of 14

  

Pre-installation Instructions 

 

When the LC/MS Arrives  

Inspecting the Shipping Cartons 

Do not open any shipping cartons. The Varian Representative opens them during 
installation.

 

Move the shipping cartons to a warm, dry, and secure area near the 

installation site.  

 

After the instrument arrives, carefully inspect the exterior of the shipping cartons for evidence of 
any damage that could have possibly occurred during shipment. Inspect the cartons for the 
following: 

 Water 

stains. 

  Cuts, punctures, or deep indentations. 

  Crushed corners or excessively abraded edges. 

  Arrow point on the Tip N Tell™ indicator is blue. 

  ShockWatch® indicator tube is red. 

Tip N Tell 

ShockWatch 

One indicator is on the 
exterior. Read and follow the 
instructions on the label. If the 
Tip N Tell arrow point is blue, 
the carton was on its side or 
tipped in transit and 
instrument damage may have 
occurred. 

One indicator is on the exterior. Read and follow the instructions on the 
label. If the tube on the ShockWatch indicator is red, the carton was 
dropped in transit and instrument damage may have occurred. 

The instrument label may be yellow, purple, or red, depending on the 
sensitivity of the instrument to impact that exceeds a specified G-level 
force.  

 

 

If no external damage is apparent, write “

Received but not inspected”

 on the receiving 

documents to indicate that the cartons were not opened. 

Systems are shipped either 

FOB Varian

 or 

FOB Destination

. The manner of shipment 

determines who is responsible for filing a claim against the carrier if the system was damaged 
in transit. Most systems are shipped 

FOB Varian

, so any damages incurred in shipment are the 

responsibility of the purchaser and the carrier. Contact the Varian office for assistance with filing 
claims and billing repairs. If the system ships 

FOB Destination

, contact the Varian office, and 

that office will file a claim against the carrier.  

Summary of Contents for varian 320-MS LC/MS

Page 1: ...114 kg 250 lb 320 MS with HTS PAL at least 103 kg 231 lb Bench does not vibrate Exhaust system is suitable Temperature maintained between 16 and 30 C 61 86 F Relative humidity maintained between 20 a...

Page 2: ...s can be analyzed After meeting all of these requirements contact the Customer Service office in your region to schedule the installation The LC MS operates reliably under carefully controlled environ...

Page 3: ...needed Allow additional room for maneuvering the shipping containers around corners and through doors Check the checklist box Entrance to the installation site is at least 92 cm 36 in wide CAUTION The...

Page 4: ...ut the modules in Figure 1 Table 1 Bench Width with the 460 LC Bench Width 212 LC 460 LC MS CPU Monitor and Keyboard Total cm 26 30 53 5 18 7 51 178 cm in 10 5 12 21 7 5 20 71 in Table 2 Bench Load wi...

Page 5: ...5 11 5 231 lb The system requires a clean flat bench The bench must be strong enough to support the weight of the modules The area under the bench must be large enough for the foreline pump If the be...

Page 6: ...have sufficient room to connect the MS to the foreline pump If the distance between the bench and the wall is less than 10 2 4 in then the bench must be at least 94 cm 37 in deep To accommodate the v...

Page 7: ...least 20 L min to a separate vent line Ensure that the exhaust system does not pull a vacuum on the API chamber Consult local regulations for the proper method of exhausting the fumes Check the checkl...

Page 8: ...er particulate matter Particulate matter may block airflow vents causing the electronics to overheat Check the checklist box Installation site is free of excessive particulate matter Power Requirement...

Page 9: ...instruments and equipment Never plug the mass spectrometer and the chromatograph into the same power source or the power source may overload Never use the free outlet on any of the power sources for e...

Page 10: ...ags or transients The voltage must meet EN IEC 61000 4 5 and EN IEC 61000 4 11 standards for voltage stability A measured ground to neutral potential of greater than 3V ac or V dc indicates grounding...

Page 11: ...erators require regular maintenance The customer is responsible for setting up the preventive maintenance procedures and schedules contact the nitrogen generator manufacturer The Varian Warranty does...

Page 12: ...ean and new volumetric flask for optional APCI Table 14 Solvents for ESI or APCI Quantity each Solvent 2 4 liter bottle HPLC grade or better water new and unopened 2 4 liter bottle HPLC grade or bette...

Page 13: ...ansit and instrument damage may have occurred One indicator is on the exterior Read and follow the instructions on the label If the tube on the ShockWatch indicator is red the carton was dropped in tr...

Page 14: ...e and the conditions of delivery accepted The process requires at least three days Spare Parts Please refer to the Quadrupole Hardware Manual which has list of spare parts for routine operation Preven...

Reviews: