Installation Note N5230-90022
Step 8. Install the 50 GHz Top to Bottom Cables
1. Place the analyzer on its side as shown in
. New parts are listed in
.
2. Insert cables W3 and W6 into the analyzer in the direction indicated by the arrows. It may
be necessary to guide the other end of the cables, on the top side of the analyzer, as they
are being inserted.
3. Loosely connect cables W3 and W6 at the locations shown in
. Once
all connectors are loosely connected, tighten the connectors.
Figure 11 50 GHz Top to Bottom Cables Installation, Bottom
Summary of Contents for N5230AU-974
Page 13: ...Installation Note N5230 90022 13 Figure 8 20 GHz Top to Bottom Cables Removal Top...
Page 15: ...Installation Note N5230 90022 15 Figure 9 20 GHz Components Removal...
Page 17: ...Installation Note N5230 90022 17 Figure 10 50 GHz Components Installation...
Page 19: ...Installation Note N5230 90022 19 Figure 12 50 GHz Top to Bottom Cables Installation Top...
Page 23: ...Installation Note N5230 90022 23 Figure 15 50 GHz Bottom Cables Installation...