5.8
Balanced flue assemblies
Assembly general:
The assembly described below applies to all flue systems:
1.
Slide the combustion gas flue pipe into the appliance flue outlet.
2.
Slide the combustion gas flue pipes into each other.
Working from the appliance each pipe must be pushed into the previous pipe
3.
Fit a non-vertical combustion gas flue pipe with a fall towards the appliance of minimal 5mm per metre
4.
Fit flanged seams oriented upwards in a horizontal section.
5.
Seal non-gastight connections with heat-and moisture-resistant aluminium tape.
Assemble all air supply pipes as indicates below:
1.
Slide the air supply pipe into the appliance inlet.
2.
Seal non-airtight connections with moisture-resistant tape.
3.
Fit insulation if necessary.
Materials to be used:
Appliance
category
Materials
Supplier
C13
Duct
ACV
Other parts
Gastec QA or ACV
C33
Duct
ACV
Duct in the case of Prefab
Gastec QA, ACV or third
parties
Other parts
C43
All materials
Gastec QA or ACV
For the combined air supply /
combustion flue system
Third parties
C53
Inlet grille
ACV
Other parts and flue cowl
Gastec QA or ACV
C63
All materials and duct
CE approved flue material
C83
Inlet grille
ACV
Main channel
Third parties
Other parts
Gastec QA or ACV