background image

Tel. +49 (0) 36965 819–0 

Fax +49 (0) 36965 819–361

11

Service-Line

ACO  H a u s t e c h n i k

6.5 Possible 

malfunctions

Operators whose plants do not possess of an au-
tomatic cleaning system are to check the cleanli-
ness of the sensors during each disposal and are 
to clean the sensor heads, if applicable.

Risk of scalding: The sensors are heated and 
reach an operating temperature of approx. 
65-75°C. After disconnecting it from the mains 
voltage, the device may still be hot for several 
minutes. 
In case of need, adequate protective measures 
must be taken.

7. Servicing

8. Spare 

parts

Setting of switching points

Switching manner

The switching points are pre-set at our works.

Depending on conductivity of water, the switching point 
is adjusted at the trim-pot. Generally, it is sufficient 
for most applications with clean tap water to leave the 
potentiometers in the most sensitive setting (left stop), 
corresponding to a switching point of approx. 12µS.

 

> If required, sensitivity for each electrode can be se-

parately adjusted. When turning against the clockwise 
direction, the electronics become more insensitive 
leading to better results with wastewater.

 

> Generally, all potentiometers should be in the same 

position. Only in the case of very different distances 
of electrodes to the reference electrode or in the 
case of long connection lines it is reasonable to 
adjust sensitivity in different ways. Following chan-
ging the cable connecting length, the setting must be 
checked.

Delays in switching behaviour may result from 
sensor surfaces coated by grease, dissolving only 
in the course of several minutes and admitting 
a proper test reading. In the case of indication 
error of the sensor, the cleanliness of the sensor 
heads must be checked.

Risk of scalding: The sensors are heated and 
reach an operating temperature of approx. 
65-75°C. After disconnecting it from the mains 
voltage, the device may still be hot for several 
minutes. 
In case of need, adequate protective measures 
must be taken.

If during operation situations develop which are not 
sufficiently described, please contact:

ACO -Service:
Telefon     +49 (0) 36965 - 819-444
Fax  

+49 (0) 36965 - 819-367

E-Mail  

[email protected]

Questions

If you have questions of any kind which are not suffici-
ently described, please contact:

ACO -Service:
Telefon     +49 (0) 36965 - 819-444
Fax  

+49 (0) 36965 - 819-367

E-Mail  

[email protected]

For spare parts, please contact:

ACO -Service:
Telefon     +49 (0) 36965 - 819-444
Fax  

+49 (0) 36965 - 819-367

E-Mail  

[email protected]

 Operation, servicing and spare parts

NOTICE

DANGER

DANGER

NOTICE

Summary of Contents for 3300.11.50

Page 1: ...tion I n s t a l l a t i o n a n d o p e r a t i n g m a n u a l GREASE LEVEL CONTROL Measuring device for grease layer thickness Please read through this manual carefully and completely prior to comm...

Page 2: ...4 1 Disassembly of appliance 5 4 2 Preparations at grease separator 6 4 3 Assembly of appliance in the grease separator 6 5 Commissioning 8 6 Operation 6 1 Function 9 6 2 Description of front wall of...

Page 3: ...ituations which could cause faults during operation of the appliance in case of non observance of directions given The product may only be applied and operated in accordance with its intended use as d...

Page 4: ...s are still flashing and when reaching 80 only 1 red LED is still lighting Emptying of the separator must be arranged Two relays with change over contact activate the aggregates signals The NC connect...

Page 5: ...rent use of the device is not permitted 4 1 Disassembly of appliance Step 2 Remove evaluation device and gripper clamps from measuring stick Step 1 Loosen spigot nut of angle plug and remove from meas...

Page 6: ...he grease separator With assembly opening Dismantle dummy plug with sealing and counter nut ACO grease separators are generally supplied with assembly opening for measuring device of grease layer thic...

Page 7: ...3 In the case of separators with high pressure HP internal cleaning fig A sensors 1 point towards HP Orbital cleaning head 2 and with separators without HP internal cleaning fig B towards a maintenan...

Page 8: ...must be carried out by an external fuse Observe operator protection Error current protective circuit Put the safety plug of the plug in evaluation device into the socket with earth contact mounted in...

Page 9: ...pacity Fuse protection of the load circuit must be car ried out externally via a fuse if required max 5A NC connection 2A NO connection For switching of higher currents relevant switching elements hav...

Page 10: ...r Evaluation at evaluation device Table C Half level signal 50 max grease storage cap Display Lights Sensors Water Grease off green red exists exists LED 4 LED 3 LED 2 LED 1 By pressing test button 1...

Page 11: ...s should be in the same position Only in the case of very different distances of electrodes to the reference electrode or in the case of long connection lines it is reasonable to adjust sensitivity in...

Page 12: ...feld Tel 49 0 36965 819 0 Fax 49 0 36965 819 361 www aco haustechnik de www aco com ACO H a u s t e c h n i k Installation and Operating Manual As per 03 2010 Origin German Manual Art no 3300 11 50 HT...

Reviews: