background image

 

 

15

                                                                                                                                                            KL II 

Series User Manual 

 

3.2 Installation site environmental requirements 

1. Before installing the fine pitch series products, test the on-site temperature and humidity to ensure that 
the temperature is within 35°C and the humidity is within 70%RH before installation; 
2. When the environment exceeds (35

, 70%RH), the screen body is in high temperature and high 

humidity, which will cause the LED lamp beads to be damp, and cause a large number of LED lamp beads 
on the screen to be damaged; 

3.3 Precautions for product installation 

3.3.1 Before installation 

1. Determine the power distribution plan: Give a specific power distribution plan based on the actual display 
size and arrangement sequence, and determine the specifications and quantity of the power distribution 
box, main power cords, and the number of power cords connected to the box. Determine the specifications 
of the sending box, video processor, and the number of network cables according to the total pixel points 
and arrangement sequence. 
2. Precautions for power distribution 

 The wiring is neat, horizontal and vertical, and non-cable wires must be laid with ducts or ducts; 

 Lay the signal wires separately from the power wires to avoid interference; 

 The wiring considers three-phase power balance, and try to have the same number of display boxes for 

each phase of electrical load; 

 The wire end of the cable needs to press the wire terminal, 

 Encode the thread head, and the overall power distribution diagram should be consistent with the actual 

wiring to facilitate subsequent troubleshooting; 

 Under the premise of considering the safe current carrying capacity, lay the cables from the distribution 

box to the display box according to the actual box arrangement; 

 For long-distance wiring, consider line loss voltage to ensure that the voltage at the display screen is 

within the allowable range; 
3. Steel structure construction: construction in accordance with the requirements of the drawings. The 
construction must be coordinated with the pipeline construction, and the person in charge of installation 
shall supervise it. 
4. Tool preparation: match and prepare the types of tools commonly used for display installation, including 
screwdrivers, wrenches, multimeters and other tools. 

 
3.3.2 During installation 

1. Installation of distribution box: The installation of distribution box must be firm and reliable. The protective 
grounding is reliable. 
2. Cabinet installation: equipment handling. Sufficient manpower must be equipped to ensure safety. Pay 
attention to handle with care, do not knock and damage the appearance and function of the cabinet. When 
installing the display screen, check whether the magnet feet are tightened. The power cord and network 
cable must be connected in place and correct, whether the network cable is inserted in place and the 
screen connection sequence is correct. 
3. Wiring sequence: first connect the box with a box-connecting power cord in series, and then use 3 main 
power cord to connect from the distribution box or socket to the bottom box. 
4. Power connection: First confirm that the power supply terminal is in the "disconnected" state, and the 
self-consumption terminal must be connected (equipment switch or distribution box, etc.). Connect the 
power supply terminal only after checking that the connection of the power supply terminal is correct. 
Connect the protective ground first, then connect the neutral line, and finally connect the phase line. After 
the power supply is connected: Check the power supply terminal switch or the equipment power distribution 
voltage, and "cut off" the power supply after confirming that it is correct. The power cord must be 
distinguished by color, ground wire, neutral wire and A, B, C and other phase wires. 
5. Cabinet adjustment: Check whether the display screen is flat and clean. Fine-tune the gap between the 
module and the module, and between the box body and the box body. When installing, make sure that the 
box body and the box body must be locked with screws to ensure the left and right/up and down flatness 
between the boxes. 
6. Power test: Before supplying power to the entire screen and providing control signals, please carefully 
check whether the power and signal lines are connected correctly; please carefully check the "L" and "N" 
lines on the AC power input port of each cabinet. "PE" line, confirm that there is no short circuit between the 
three (measured with a multimeter). 
7. Power-on detection: fault judgment, check the appearance. Power-on detection whether there is a bad 
screen and whether the text output is correct; if a fault occurs, judge and eliminate the fault based on the 

Summary of Contents for B5515-2-00

Page 1: ...KL II Series User Manual Absen Optoelectronic Co Ltd KL1 2 II KL1 5 II KL1 8 II KL2 5 II...

Page 2: ...s 15 3 3 Precautions for product installation 15 4 PRODUCT INSTALLATION 16 4 1 Ground stack installation 16 4 2 Wall mounted installation 18 4 3 Rigging installation 20 4 4 Trim pieces installation 21...

Page 3: ...Do not ignore using the grounding plug or else there is a risk of electric shock During a lightning storm please disconnect the device s power supply or provide other suitable lightning protection If...

Page 4: ...emove parts Do not use the product in case ambient temperature is over 40 Beware of injury Warning Wear a helmet to avoid injury Ensure any structures used to support fix and connect the equipment can...

Page 5: ...ng Changes or modifications to this unit not expressly approved by the party responsible for compliance could void the user s authority to operate the equipment NOTE This equipment has been tested and...

Page 6: ...rate which makes it capable of any complex and variable commercial display environment The product is mainly used in Brand Chain Shopping Plaza Hotel Ballroom TV Station Bank Church Theater Enterpris...

Page 7: ...0 600 Refresh Rate Hz 3840 3840 3840 3840 Gray scale bit 14 14 14 14 Contrast Ratio 4000 1 4000 1 4000 1 3000 1 Color Temperature K 2500 9500 adjustable Viewing Angle H V 140 120 160 140 160 140 160 1...

Page 8: ...KL II Series User Manual 8 1 3 Panel size Side view and Rear view Unit mm 1 4 Module size 320 180 front view Unit mm...

Page 9: ...of installation front rear integrated floating type socket Handle Installation screw hole Side splicing screw hole Side cable through hole Z axis adjusting screw hole Upper lower splicing screw hole...

Page 10: ...trip Optional Wall mounting installation accessories including double and triple back strip Hanging bar Optional Rigging installation accessories including single and double hanging bar Double back st...

Page 11: ...plate Default Ground stacking installation accessories Trim pieces Video wall edge decoration accessories Upper trim pieces Left side trim pieces from front Lower trim pieces Right side trim pieces fr...

Page 12: ...There s a built in vertical power cable inside the panel Power In Cable 10 meters long power cable The official standard Others specification Optional Location Trim pieces specs 9 types Left Right Do...

Page 13: ...13 KL II Series User Manual Package Modules and Cabinets are packaged separately Modules 40 modules in 1 carton 4 cartons in 1 pallet Cabinet 5 cabinets in 1 carton 4 cartons in 1 pallet...

Page 14: ...agon wrench Install the screws between the LED cabinets spanner Install bolts PH2 screwdriver Maintenance and disassembly Module power supply receiving card screws multimeter Measuring power cord and...

Page 15: ...wrenches multimeters and other tools 3 3 2 During installation 1 Installation of distribution box The installation of distribution box must be firm and reliable The protective grounding is reliable 2...

Page 16: ...UCT INSTALLATION Product installation type NO Installation type remark 1 Ground stack installation Install the LED cabinets on the steel structure with the connecting plate 2 Wall mounted installation...

Page 17: ...latness of the structure splicing from the front Step 4 Install the second layer fix LED cabinets with M6x30mm bolts between top and bottom and then tighten them with a socket hexagon wrench Note Duri...

Page 18: ...the second layer fix LED cabinets with M6x30mm bolts between top and bottom and then tighten them with a socket hexagon wrench Note During the installation process ensure the flatness of the splicing...

Page 19: ...the wall and make a mark on the wall take a cabinet assembly installation unit to the wall and mark the fixing position of the drilling hole with a marker Install self tapping screws on wooden walls...

Page 20: ...connect the left and right hanging beams and keep them on the same horizontal line Note When installing the hanging beam the arrow direction on the top of the hanging beam is the same as the front of...

Page 21: ...tural installation of other cabinets 4 4 Trim pieces installation This product supports hemming installation Absen provides hemming for project selection The left and right sides of the screen body ar...

Page 22: ...tion of the left or right hemming 5 When installing the left or right side hemming use the hexagonal screw to pass through the hole on the cabinet body from the inside to the outside to fix it The upp...

Page 23: ...The quantity will be different when unable to confirm please contact our customer service department According to power points our distribution boxes are mainly 15KW 30KW 60KW 90KW 120KW 150KW 180KW...

Page 24: ...male and female plugs of the power cord that comes with the cabinet Take the 5x5 KL1 5 cabinet as an example to introduce the connection method of the power cord The total power consumption of 25pcs...

Page 25: ...s connection This product cannot store or display video content solely on itself To perform normal work the screen requires video source from the output device such as PC laptop media player etc and o...

Page 26: ...t the line is normal power on the cabinet to work After confirming that the screen is energized normally connect the computer and the sending box and use the NovaLCT software to configure the LED disp...

Page 27: ...e quickly removed with a vacuum suction tool Attach the front maintenance tool to the surface of the faulty module to be taken out press the switch and wait for 5 seconds and then take out the module...

Page 28: ...remove the modules on the cabinet use a PH2 screwdriver to remove the 2 screws fixing the receiving card and replace the failed receiving card HUB board maintenance illustration use the front maintena...

Page 29: ...specially strong lightning weather The large screen power supply must be supplied step by step because the maximum power state of the entire screen will have an impact on the entire power distribution...

Page 30: ...pt the pre heating method 30 50 of the brightness is preheated for more than 12 hours and then adjusted to normal brightness 80 100 to light up the screen so as to remove the moisture so that there is...

Page 31: ...ding card is powered on and whether the running indicator is flashing 5 Replace the sending card 6 Connecting the computer to an LCD display check whether there is output on video card 7 Update the vi...

Page 32: ...e is inserted into the wrong data port 5 Check whether the sending card data port is malfunctioning 6 Re add the multi function card 7 Replace the multi function card 8 Replace the sending card 8 No f...