STEP 3.
REAR
SIDE
FRONT
CENTRE
REAR
FRONT
REAR
SIDE
FRONT
STEP 3A.
MARK OFF THE SIDE BEAMS TO THE DIMENSIONS SHOWN BELOW. THESE ARE THE
POSITIONS FOR LOCATING THE COLUMN TOP BRACKETS, TO WHICH THE COLUMNS AND
CROSS BEAMS WILL BE LATER CONNECTED.
THIS SET OF FOUR
HOLES MUST MATCH
THE FOUR HOLES IN
THE CROSS BEAM.
THE REAR RHS COLUMNS ARE 50mm SHORTER THAN THE FRONT RHS COLUMNS.
THIS PRODUCES ABOUT A ONE DEGREE FALL IN THE ROOF, TO ALLOW RAINWATER
TO FLOW TO THE REAR DOWNPIPE.
THEREFORE, TO ENSURE THAT THE COLUMNS WILL REMAIN VERTICAL WHEN THE
STRUCTURE IS RAISED, EACH COLUMN TOP BRACKET MUST BE OFFSET BY 6mm AS
SHOWN BELOW. YOU CAN SEE BELOW HOW THE END RESULT WILL KEEP THE COLUMNS
VERTICAL BUT TILT THE ROOF.
FLUSH WITH INSIDE
FLANGE AT THIS POINT
FLUSH WITH INSIDE
FLANGE AT THIS POINT
FLUSH WITH INSIDE
FLANGE AT THIS POINT
FIT AN EXTRA SPLICE PLATE IN EACH SIDE EDGE
BEAM, OVER THE FRONT AND REAR COLUMN
POSITIONS AND FASTEN WITH TEK SCREWS.
MARK THE HOLE POSITIONS FOR THE FOUR HOLES TO BE DRILLED IN THE BEAMS AT
EACH LOCATION, AND DRILL 10mm HOLES. DO NOT FASTEN THE COLUMN TOP
BRACKETS TO THE EDGE BEAMS AT THIS STAGE.
6mm
6mm
6mm
1080
1670
1670
1080
ABSCO INDUSTRIES
ASSEMBLY INSTRUCTION MANUAL
CARPORT MODEL: CPDW50
10-05-2017
Absco Industries
Skillion Carport Model: CPDW50
PAGE 09