- 64 -
000067BG
7 - Operation
D
isplay access and settings
After the commissioning of the inverter, it is possible/necessary to set the
configuration of the inverter by accessing the “Account Settings” from
the display. The following are the main adjustable parameters (see the
section dedicated to the “
Menu descriptions
”)
•
Address RS485
: settings required in the case of system monitoring
using the RS485 board
•
Vstart
: setting required in the case it is requested by the configuration
during the system requirement phase (“Vstart” parameter)
•
MPPT scan
: allows you to carry out a search for the maximum power
point with sensitivity and adjustable time intervals (“MPP” parameter).
•
Analogue inputs setting (where present)
: allows you to set the pa-
rameters of the analogue sensors connected as the input (“Analogue
Inputs”).
•
Input Strings (where present)
: setting necessary to carry out checks
on the status of the fuses and on the current imbalance of the strings
present in the input (“Fuse control” parameters).
•
Reactive power input setting (where present)
: setting necessary to
manage the reactive power input into the grid in different ways (“Reactive
Power parameter”)
•
Limitation active power setting (where present)
: setting necessary
to set a limit on active power output of the inverter (“Power reduction”
parameter)