20/72
TLE Series 625 to 1000 PurePulse™ UL S2
UPS Installation Guide / REV-B
Fig. 4.4.1-8 TLE Series 1000 – UPS cabinet floor fixing points
Fig. 4.4.1-9 TLE Series 625 to 1000 – RPA Parallel System disposition
In case of Parallel System, try to place the UPS modules in sequence of their numbers (marked
on the packing).
If the units are positioned “side by side”, the side panels must be mounted on all units.
Remove the side air inlet grids on the intermediate units to run the control bus cable
connections.
Ø 0.53
" / 13
.5mm
29
.53
"
/ 7
50
m
m
34
.0
6 "
/
86
5
mm
2.13 " / 54 mm
27.56 " / 700 mm
27.56 " / 700 mm
33.46 " / 850 mm
143.50 " / 3645 mm
3.94 "/100 mm
3.94 "/100 mm
Frontal side
TLES_UL_1000_S2_UPS fixing_ABB_02
Power Section cabinet
In/Out Section cabinet
7.87 "
200 mm
2.
37 "
60
mm
2.37 "
60 mm
2.37 "
60 mm
17.72 "
450 mm
12.80 "
325 mm
UPS
3 - 4 - 5 - 6
UPS 1
UPS 2
TLES_UL_1
000_S2_R
PA dispos
ition_ABB
_01US