
10
and all components are correct, modify the Methane (C1) to
receive 100%.
16D
If changes were made in the Calibration Setup, click the Send
button. Afterwards, click the Re-read button to verify changes,
and then click the Close button on Calibration Setup.
16E
On the Operation screen, the unit will indicate that it is Hold
mode. If this does not occur, wait until the cycle finishes and
moves into Hold.
16F
Click the Cal button on the left side of the screen. The Current
Mode indicator for Calibrate will illuminate. Additionally, a visual
indicator of the flowing calibration stream will display. The Next
Mode should still indicate Hold, and the unit will go back into
Hold mode when the calibration process is finished. If using 2
Purge cycles and 3 cycles to average, the calibration process will
take approximately 25 minutes.
Operation Screen (Cal Mode)
NOTE:
On the Operation screen, if enabled, a stream will display
information on the stream blocks, shown by stream 1 above. This is
always process stream data for that stream. If it is a calibration stream
only, the data shown on the blocks is still process stream data and not
calibration data. As such, it is not relative. It should be noted that if
enabled, a calibration stream is grayed out during Calibration.
Start-up