QUICK START GUIDE
Page 5
© 2021 ABB. All rights reserved.
Step 7
-
Connect Bullet Circuit Breaker Loads
-
skip if not present
(continued)
Step 8
-
Connect Snapak Circuit Breaker Loads
-
skip if not present
1.
Verify that breaker is OFF or not installed.
2.
Remove detachable terminal block
3.
Insert load and load return wires Strip 0.4 in (10 mm)
8 AWG (6 mm2) max.
4.
Torque to 6.5 in
-
lb (0.75 Nm).
5.
Pull wires to verify.
6.
Insert detachable terminal block fully.
Step 9
-
Connect GMT Style Fuse Loads
-
skip if not present
skip if not present Connections for Load GMT Fuses to GMT terminal blocks identified as
“
-
48
VDC
”
and
“
RTNS
”
on
labels above each row of terminals blocks.
Wire Size: 24
-
12AWG
Strip Length:
0.35”
(9mm)
1.
Verify that fuse is not installed.
2.
Strip wires
3.
Insert wires into terminal blocks labeled
-
48VDC and associated RTNS.
4.
Tighten screw
-
4 in
-
lb (0.45 Nm).
5.
Pull wire to verify.
Bullet Breaker Connections
(ID Label and Breaker landing covers not shown)
Cover Screws
-
Return Lug Landings
-
48V Lug Landings
Screw
Snapak Breaker Connections
Detachable Terminal Block
-
48V Load
Load Return
3
-
Circuit Blocks
-
Load Only