QUICK START GUIDE
Page 3
© 2021 ABB. All rights reserved.
Step 4
-
Connect Shelf DC
(continued)
Step 5
-
Connect Communication Wires
Connectors are on the rear of the shelf.
1.
Connect alarm cable between Primary Distribution Shelf and adjacent Primary Rectifier Shelf (with controller)
(if present)
-
cable provided.
2.
Connect alarm cables between all Distribution Shelves.
RETURN bus Connections
covers shown
-
48V bus Connections
covers removed
2 Adjacent shelves
Dual Lug Landings
(stand
-
alone Shelf)
Inter
-
shelf bus
Alarm Cable Primary
Distribution Shelf to
Primary Rectifier Shelf
Primary Rectifier Shelf
(with Controller)
Primary Distribution
Shelf
Alarm Cable Shelf
to Shelf
Supplemental Distribution
Shelves
SPS System
NE or CP System