42/24-30 EN Rev. 1
EL6010 Gas Analyzer in Category 2G Operator’s Manual
13
Chapter 2
Install the Gas Analyzer
Unpack and Install the Gas Analyzer
CAUTION!
The EL6010-CU control unit weighs approx. 19 kg! The EL6010-... analyzer unit
weighs approx. 26 kg! The following points should be observed:
•
Two persons are needed for unpacking and installation of the analyzer unit.
•
The installation location must be stable enough in order to support the
EL6010 gas analyzer’s weight.
Step Action
1
Remove the control unit and the analyzer unit with the respective
protective packaging from the shipping box.
2
Remove the protective packaging and place the control unit and the
analyzer unit in a clean location.
Unpack the
Gas Analyzer
3
Remove the adhesive packaging residue from the control unit and the
analyzer unit.
If there is shipping damage that points to improper handling, file a damage claim
with the shipper (railway, mail or freight carrier) within seven days.
Make sure the enclosed accessories are not lost (see Section “Items Delivered”,
page 10).
Keep the shipping box and packaging material for future shipping needs.
Gas Path
Seal Integrity
Verification
The seal integrity of the sample gas path and reference gas path (if applicable)
within the analyzer unit is factory-tested with helium at a leak rate of
< 2 · 10
–4
hPa l/s.
Since gas path seal integrity can be compromised during shipping of the analyzer
unit (e.g. by strong vibration) a seal integrity check should be performed on site
prior to startup.
For information on checking gas path seal integrity see Section “Inspection and
Maintenance”, page 43.