7  Commissioning 

7.1  General procedures 

 

All operations regarding commissioning must be carried out by suitably 
qualified customer personnel with in-depth knowledge of the apparatus and 
the installation itself.  

 

 

Do not open the disconnecting switch under charge using a common pole, as 
it could cause an arc that could damage the personnel or the equipment. The 
disconnecting switch has horns to be used with a load break tool to carry out 
this kind of operation.  

 

 

8  Maintenance 

Test the correct operation of electronic sectionalizer on a regular basis, preferably while 
maintenance on head recloser is made: 

- Check the closing system. 

- Check that the interlocking bolt turns freely. The tensioning device support should move 
easily and the spring should be sufficiently tightened so that the support may reset when 
the system opens following the operation of the sectionalizer. 

- Check that the mobile lever and the lower support of the AutoLink move easily at the 
joint. Clean and lubricate the joint surfaces of both pieces. 

- Keep contact zones clean and place a thin film of conductive grease on those zones. 

Test should be carried out on a laboratory with the appropriate equipment to simulate 
service conditions. For this operation it is recommended to contact ABB for requesting 
testing procedures. 

 

Summary of Contents for AutoLink

Page 1: ...TEHI95094 rev 1 AutoLink 15kV 27kV 33kV Mounting Instructions...

Page 2: ...tice and safety in the workplace are constructed Strictly follow the information given in this instruction manual Check that the rated performance of the apparatus is not exceeded during service Check...

Page 3: ...3 Checking on Reception 4 4 Storage 5 5 Description 5 6 Installation 5 6 1 General 5 6 2 Installation and service conditions 5 6 3 Initial Setting or Previous Setting Modification Instructions 6 6 4...

Page 4: ...into service commissioning and maintenance operations must be carried out by suitably qualified personnel with in depth knowledge of the apparatus 2 Packing and Transportation The AutoLink Sectionaliz...

Page 5: ...rom any flammable materials and at a temperature between 5 C and 45 C In any case avoid any accidental impacts or positioning which stresses the structure of the apparatus 5 Description The AutoLink E...

Page 6: ...g Modification Instructions Remove the contact cap Fig 1 A with a 34mm fork spanner holding the base Fig 1 B with the hand Check condition of O ring Fig 2 E and replace if necessary applying grease on...

Page 7: ...nt and counts are selected cover the dipswitch with a generous amount of silicon grease Fig 3 supplied with AutoLink Figure 3 Check the condition of the O Ring Fig 2 E and apply silicon grease Fig 4 F...

Page 8: ...0 Nm without damaging the O Ring Fig 5 Figure 5 6 4 AutoLink Repositioning Push the interlocking bolt Fig 6 until blocked it will spin freely but it will not reset Do not strike the bolt nor use any t...

Page 9: ...until it is firmly blocked Fig 8 Figure 8 Place the pole in the tube inferior eyelet Fig 9 and position in the isolating support body Figure 9 Withdraw the pole and place it in the tube s superior ey...

Page 10: ...regular basis preferably while maintenance on head recloser is made Check the closing system Check that the interlocking bolt turns freely The tensioning device support should move easily and the spr...

Page 11: ...TEHI95094 rev 1 11 11 Copyright 2007 ABB All rights reserved Document Title AutoLink Document No Date Rev Ind No of Pages Page TEHI95094 EN 1 11 11...

Reviews: