Operator’s Manual ACF-NT, ACF-NT V0309
42/23-572 EN Rev. 5
Chapter 1
Startup
Restart
Initial startup of the analyzer system should be performed by trained personnel of
the manufacturer or the supplier.
Restart
Perform the following steps when restarting the analyzer system e.g. after
maintenance or a facility shutdown.
Activating the
Instrument Air Supply
Set the initial pressure (p
e
= 5–7 bar).
Check the moisture indicator in the air purifier: green = OK, yellow = not OK.
Activate the instrument air supply to the FTIR spectrometer at the earliest 1 hour
after activating the power supply. This will ensure the air is sufficiently dry.
Activating the
Power Supply
Make sure all circuit breakers (fuses) are deactivated.
Turn on the main switch.
Activate the circuit breakers (fuses) – starting with those for the FTIR
spectrometer.
Connecting the
Filtered Air
Check the filtered spectrometer purge air flow rate and set it to approx. 200 l/hr
if necessary.
Checking the
Temperature
Check the temperature of the heated components (gas sampling probe, filter
unit and sample gas line; desired value 180 °C).
Starting the
VOC Analyzer
Start the VOC analyzer following the instructions and information in the AO2000-
MultiFID14 Start-up and Maintenance Manual (Publication No. 41/24-105 EN).
Warm-Up Phase
The warm-up phase takes approx. 3 hours.
Calibration
Start the manual zero correction (see section “FTIR Spectrometer Zero