GX-A/GF-A Maintenance manual
Page 17
5. Force Motor Disassembly and Reassembly
This chapter describes the procedures and notes for the flexure assembly replacement,
bobbin cleaning, and adjustment after reassembling the force motor.
Notes: The disassembly and reassembly should take place in a dust free environment.
Adjustments and confirmations are needed after reassembly for linearity,
repeatability, creep, hysteresis and corner load error.
Temperature adjustment is also needed since the balance is affected by
tightening torque or stress. If you do not have the proper facilities to do the
temperature adjustment, do not attempt to adjust the temperature feature.
Jig set (7PA:GXA-JIG) for GX-A/GF-A mechanical unit disassembly
and reassembly
●
Other tools required:
A square
Allen head screw
:
M5x10 (3pcs)
M2, M4 screwdriver
M4x15 (1pc)
M4, M5 torx wrench
M4, M5 allen wrench Pan head screw
:
M3x
8
0 (1pc)
5.5mm spanner M4
x
8 (6pcs)
A soldering iron M4
x
10 (2pcs)
A base jig
GXA-1/8
A spacer for positioning
the beam(1)
GXA-2/8
A bolt for holding
the beam(1)
GXA-3/8
A board for positioning
the beam(1)
GXA-4/8
A plate for positioning
the beam(1)
GXA-5/8
A jig for positioning the
fulcrum flexure(1)
GXA-6/8
A jig for positioning the
force coil bobbin
GXA-7/8
A jig for assembling
the beam(2)
GXA-8/8
Summary of Contents for GF-A Series
Page 51: ......