74
40-D043 Revision C 5-May-17
Position:
Shows the position of the build status depending on original CAD Z coordinate. The
units, inches or millimeters, will be consistent with the units used in the build file.
Percent:
With 0% as the start and 100% as the end, shows the percentage completed of the
current build.
Duration:
With 0:00 as the start and the projected time of completion as the end, shows the time
that has elapsed at the current build.
Time:
In real time, this clock shows the time that the build started, the current time, and the
projected time at the end of the build.
Note: The format of the values in the right hand column will change depending on the
dropdown selected.
The
Build Status
dropdown enables you to change the units of the status of the build.
--- units can be in inches for Position.
--- percentage for Percent
--- hours, minutes, and seconds for Duration and Time (clock).