5
© Copyright 2014 Zoeller Co. All rights reserved.
QWIK JON
®
ULTIMA QWIK REFERENCE GUIDE
STEp 1
LOCaTION SELECTION
plan your new installation carefully.
floor:
The floor should be structurally sound and level within 3 mm (1/8"). If the
floor is not level, use hydraulic cement or similar material to level the floor.
Water:
A water supply will be needed to operate the toilet. Usually a DN15 (1/2")
line with a shut-off valve is sufficient.
Electrical:
A receptacle of the appropriate voltage will be needed to supply electrical
power to the pump.
Sewage:
Access to a sewage line is required. The Qwik Jon
®
Ultima requires a DN25
(1" ) (or DN20 [3/4"] if your codes permit) sewage discharge line to connect to an
existing sewage line. A ball or gate valve should be installed in the discharge line.
Vent:
Access to a vent pipe is required. The use of a mechanical vent system is
NOT recommended as the toilet will not flush.
NOTE:
If a built-in installation is to be used, locate the pump unit in an area that
will allow access to the pump and switch.
OUTLET
WATER
SUPPLY
DISCHARGE
PIPE
VENT
PIPE
LEVEL FLOOR
BALL OR GATE VALVE
SOLD SEPARATELY.
SK2588
STEp 2
LEVELINg Of pUMp UNIT
CAUTION
Do not use wooden shims to level the pump unit!
CAUTION
Ensure that nails, screws or other sharp objects do not puncture the pump unit!
Level the pump unit to within 3 mm (1/8") using hydraulic cement or similar material.
SK2589
STEp 3
ROUgH-IN
1)
Position the pump unit a minimum of 3 mm (1/8") from the wall
with the inlet facing forward. Attach the bellows to the inlet using
the worm drive clamp provided.
2)
Place the toilet in front of pump unit aligning the discharge of the
toilet with the inlet of the pump unit. Make sure that the bellows
will bridge the gap adequately for final installation. The toilet
tank should be a minimum of 13 mm (1/2") from the wall.
3)
Lightly mark the locations of the pump unit, toilet and closet
bolt locations on the floor. Lightly mark the wall with the height
of the pump unit and the bottom and sides of the toilet tank to
ensure against interference from pipe runs later.
4)
Remove the toilet from the pump unit and set it aside.
SK2590
(STAND-ALONE INSTALLATION)
(BEHIND-THE-WALL INSTALLATION)
1)
Installing the grinder unit behind a wall will require an
extension kit (P/N 10-3050) sold separately.
2)
Place the toilet assembly a minimum of 13 mm (1/2") from
the wall and mark the closet bolt locations on the floor.
3)
Measure the appropriate length of DN90 (3½") Schedule
40 PVC pipe provided with the extension kit and cut it to
length. See sketch below.
4)
Set toilet aside.
CAUTION
Toilet assembly is top heavy. Take special
precautions to ensure that toilet does not tip over and break.
SK2634