1/4-20 x 1-1/8"
S.S. SCREWS
DISCHARGE PIPE
1-1/2" SLP x NPT
2" SLP x NPT
CORD SEAL
1/4-20
S.S. NUTS
(TORQUE TO 35 IN-LB)
SEE NOTE
(APPLY SEALANT TO THREADS)
CAP
O-RING
KEY
TRAP INLET
GFCI
OUTLET
GFCI
OUTLET
CORD SEAL
CAP
UNION
(PURCHASED SEPARATELY)
CHECK VALVE
DISCHARGE PIPE
DISCHARGE PIPE
CHECK VALVE
CAP
UNION
(PURCHASED SEPARATELY)
CORD SEAL
INLET
INLET
INTERNAL TRAP INSTALLATION
STANDARD INSTALLATION
STEP 5
Final Assembly
NOTE: External plumbing configuration will vary depending on the location of basin, location of main stack and
available space.
5.1)
Place the pump in the basin as shown in Figure 5.1.
NOTE: I
f installing the internal trap, rotate the tail pipe to the orientation shown in Figure 5.1.
5.2)
Install the lid components as shown in Figure 5.2.
NOTE:
Pull excess cordage through the opening and install the cord seal as shown in Figure 5.3A.
Insure o-ring is in the cap before installation.
5.3)
Place the basin assembly in its final position and complete plumbing. Secure all connections
(shown in 5.3A or 5.3B).
STEP 6
Initial Testing of Drain Basin System
6.1)
Plug the cord into a properly grounded GFCI receptacle.
6.2)
Fill tank with water.
6.3)
Check all plumbing for leaks as the basin fills.
6.4)
Verify that the pump starts and stops.
6.5.) Check the discharge line for leaks as the pump empties the basin.
6.6.) Repeat steps 6.2 to 6.5 as necessary to insure proper operation.
6.7.) If problems persist, refer to the troubleshooting guide located on page 2 of this manual.
Figure 5.1
Figure 5.2
SK2005
SK2007A
*
*
Figure 5.3A
Figure 5.3B
SK2006
*
CHECK VALVE MUST BE
PURCHASED SEPARATELY
FOR MODEL 104 & 132-0005.