4. Location Selection
5. Foundation Requirement
As shown in the figure
As shown in the figure
· At least 800mm of clearance shall be reserved at the back of the cabinet for the maintenance access of the fan
· At least 1000mm clearance shall be reserved in front of the cabinet for door opening
· The floor shall be flat with 1499*1444 leveled area; four M12*30 anchor bolts shall be driven into the ground for
installation of the cabinet
· Reinforcement is required at the perimeter of 130mm and the transom of 90mm to achieve a load bearing capacity of
2.5T
· Location No. 1 shows a hole for running the main cable; location No. 2 shows a hole for running the Ethernet cable and
UPS power cable
4