4. Location Selection

5. Foundation Requirement

As shown in the figure

As shown in the figure

· At least 800mm of clearance shall be reserved at the back of the cabinet for the maintenance access of the fan

· At least 1000mm clearance shall be reserved in front of the cabinet for door opening

· The floor shall be flat with 1499*1444 leveled area; four M12*30 anchor bolts shall be driven into the ground for 

installation of the cabinet 

· Reinforcement is required at the perimeter of 130mm and the transom of 90mm to achieve a load bearing capacity of 

2.5T 

· Location No. 1 shows a hole for running the main cable; location No. 2 shows a hole for running the Ethernet cable and 

UPS power cable 