3.
Glue the barrel union and nut (3) to the cell inlet plumbing
4.
Fit locking ring (2) as shown to the inlet of the cell and connect inlet plumbing
and secure with nut (3)
5.
Position Cell so that it is vertical and click the foot assembly (7) to the Locking Ring
d) There is a one-way check valve inside of the return side of the cell to ensure proper flow
sensor operation.
Important
:
Do not fit an isolating valve between the cell and the pool wall.
The cell is
fitted with an internal restrictor valve to enable the removal of the electrode for inspection and
cleaning.
e) Gluing: The cell unions are moulded ABS polymer. They can be glued to PVC using PVC
cement. First clean both surfaces with solvent cleaner then apply glue to both surfaces.
Assemble glued joint and hold in place for at least 30 seconds. Allow 24 hours to set before
turning on the circulation system.
WARNING
: Do not turn off the pump before turning off the Zodiac EZ SALT Chlorine Generating
Device.
2. Installing the power pack
Determine the proper area to mount the power pack:
a) Position at least 3 metres (10 feet) horizontally away from the pool.
b) Place power pack within 2 metres (6 feet) of a GFCI protected mains power outlet. There is
7.5 metres (25 feet) of cell lead.
c) Power pack must not be installed directly above any other heat source such as filter, pump or
heater. It must be at least 30 cm (12 inches) from the ground to allow free circulation or air
around it.
d) Do not enclose the power pack in a box.
e) A shaded position away from rain and direct sunlight is preferable, though not essential.
Mount the power pack to a wall or post using the screws provided with 150mm between the
centres of each screw. If the power pack is to be installed on a post, first install on a flat panel of
suitable waterproof, non-flammable material at least 30 cm (12 inches) wide by 30 cm (12 inches)
high.
3. Connecting the power pack to the cell
10