Direction Interchange of the Boom Arm
For example, when L is changed to R, the operation steps are as follows:
1.
Please turn off the electricity before starting. Remove the spring, spring hanging arm,
and boom.
2.
Change the direction of the Spindle Connecting Arm and the linkage Arm.
3.
Turn the Limited Block to the other direction.
4.
After the mechanical operation, you need to set the movement parameter L-D on the
motherboard, such as changing from L to R, then the value of this parameter should be
set from 0 to 3.
Spring Adjustment
If the boom arm shakes when it rises, then you can adjust the spring loosely, and if the