STT113 TOWER CRANE OPERATION AND SERVICE MANUAL
3B
-
9
4. Periodical inspection item
1). Electricity
Inspection item
Cycle
After each erection
Half a month
Check the max. supply voltage of tower crane
∨
Check that whether the connection of earth
wire is in good condition
∨
∨
Check the connecting condition between
tracks connection and between tracks and
earth conductor
∨
Check the earth resistance of tower crane
∨
Check the insulation resistance of electric
equipment
∨
Check the motion of relay in each circuit,
which can protect the tower crane safety
∨
Check the insulation resistance of motor
∨
Check the contact condition of switch contact
in circuit
∨
Check that whether the connecting terminal
in each electrical panel and resistance box
(including the inner binding screw and nut) is
tightened up.
∨
∨
Ensure that every electrical component is in
good condition, and connecting wire for them
has already been tightened up
∨
∨