Maintenance and inspection
9
-
49
1 Trained staff
2 YASKAWA trained staff
3 YASKAWA personnel
Item numbers
1
Schedule (h)
Method
Operation
To be per-
formed by:
Daily
1000
12000
24000
36000
1
2
3
1
Alignment marks
Visual inspection
Check alignment mark correspondence and dam-
age at the zero position.
2
External cables
Visual inspection
Check cables for damage.
3
Working area and robot
Visual inspection
If the working area is dirty, it must be cleaned. Check
the robot for damage and external cracks.
4
Fastening bolts of the base
plate
Using a correspond-
ing tool,
tighten loose screws (replace if necessary).
5
Fixing screws of the cover
Using a correspond-
ing tool,
tighten loose screws (replace if necessary).
6
Power input module
Manually
Check for loose connections.
7
Toothed belt for B- and T-axes
Manually
Check for tension and wear
8
Motors for S, L, U, B, and R-
axes
Visual inspection
Check for grease leakage.
9
Wiring harness in the robot
(wires of the S-, L- and U-axis)
Visual
Check for damage and clean this part if it is dirty.
Visual inspection
with multimeter
Check the bushing between the connector on the
stand and the intermediate connectors by manually
moving the wires. Check the protection spring
2
.
Replace
3
10
Wiring harness in the robot
(wires of the B- and T-axis)
Visual inspection
with multimeter
Check the wires between the terminals for wear.
Exchange
Содержание GP25-12
Страница 1: ...ROBOTICS YYR 1 06VXH25 A10 GP25 12 Standard Operating and Maintenance Manual...
Страница 51: ...Maintenance and inspection 9 51 Fig 9 2 Inspection intervals...
Страница 56: ...Maintenance and inspection 9 56 9 3 Wrist unit Sealing part U arm Cover Gasket U arm 1 2 3...
Страница 77: ...Parts lists 11 77...