5 Installation Procedure
EN 14
YASKAWA Europe
YEU TOEP C710616 87A - A1000 Option Powerlink - Installation Manual
Prior to Installing the Option Card
Prior to installing the Powerlink Option, wire the drive and make necessary connections to
the drive terminals. For more information on wiring and connecting the drive, refer to the
manual packaged with the drive. Verify that the drive runs normally without the option
installed.
Installing the Option
1.
Shut off power to the drive, wait the appropriate amount of time for voltage to
dissipate, then remove the operator (9) and front cover (11). Refer to the drive
manual for direction on removing the front cover.
2.
Insert the CN5 connector on the option (5) into the CN5-A connector on the drive
(3), then fasten it into place using one of the screws included with the option.
Connect the ground wire (7) to the ground terminal (4) using one of the screws
provided with the option.
Note:
There are only two screw holes on the drive for ground terminals. If three option
cards are connected, two of the ground wires will need to share the same ground
terminal.
Do not operate damaged equipment.
Failure to comply may cause further damage to the equipment.
Do not connect or operate any equipment with visible damage or missing parts.
Tighten all terminal screws to the specified tightening torque.
Loose electrical connections could result in death or serious injury by fire due to overheating of
electrical connections.
Do not use unshielded cable for control wiring.
Failure to comply may cause electrical interference resulting in poor system performance.
Use shielded twisted-pair wires and ground the shield to the ground terminal of the drive.
Properly connect all pins and connectors.
Failure to comply may prevent proper operation and possibly damage equipment.
Check wiring to ensure that all connections are correct after installing the option card and
connecting any other devices.
Failure to comply may result in damage to the option card.
NOTICE