5. At the Supplier’s request, the Purchaser shall declare within a reasonable period of time whether it, due to the delayed Supplies, rescinds
the contract or insists on the delivery of the Supplies.
6. If dispatch or delivery, due to Purchaser’s request, is delayed by more than one month after notification of the readiness for dispatch
was given, the Purchaser may be charged, for every additional month commenced, storage costs of 0.5 % of the price of the items of the
Supplies, but in no case more than a total of 5 %. The parties to the contract may prove that higher or, as the case may be, lower storage
costs have been incurred.
Article V: Passing of Risk
1. Even where delivery has been agreed freight free, the risk shall pass to the Purchaser as follows:
(a) if the delivery does not include assembly or erection, at the time when it is shipped or picked up by the carrier. Upon the Purchaser’s
request, the Supplier shall insure the delivery against the usual risks of transport at the Purchaser’s expense;
(b) if the delivery includes assembly or erection, at the day of taking over in the Purchaser’s own works or, if so agreed, after a successful
trial run.
2. The risk shall pass to the Purchaser if dispatch, delivery, the start or performance of assembly or erection, the taking over in the
Purchaser’s own works, or the trial run is delayed for reasons for which the Purchaser is responsible or if the Purchaser has otherwise failed
to accept the Supplies.
Article VI: Assembly and Erection
Unless otherwise agreed in written form, assembly and erection shall be subject to the following provisions:
1. Purchaser shall provide at its own expense and in due time:
(a) all earth and construction work and other ancillary work outside the Supplier’s scope, including the necessary skilled and unskilled labor,
construction materials and tools;
(b) the equipment and materials necessary for assembly and commissioning such as scaffolds, lifting equipment and other devices as well
as fuels and lubricants;
(c) energy and water at the point of use including connections, heating and lighting;
(d) suitable dry and lockable rooms of sufficient size adjacent to the site for the storage of machine parts, apparatus, materials, tools,
etc. and adequate working and recreation rooms for the erection personnel, including sanitary facilities as are appropriate in the specific
circumstances; furthermore, the Purchaser shall take all measures it would take for the protection of its own possessions to protect the
possessions of the Supplier and of the erection personnel at the site;
(e) protective clothing and protective devices needed due to particular conditions prevailing on the specific site.
2. Before the erection work starts, the Purchaser shall unsolicitedly make available any information required concerning the location of
concealed electric power, gas and water lines or of similar installations as well as the necessary structural data.
3. Prior to assembly or erection, the materials and equipment necessary for the work to start must be available on the site of assembly or
erection and any preparatory work must have advanced to such a degree that assembly or erection can be started as agreed and carried
out without interruption. Access roads and the site of assembly or erection must be level and clear.
4. If assembly, erection or commissioning is delayed due to circumstances for which the Supplier is not responsible, the Purchaser shall
bear the reasonable costs incurred for idle times and any additional traveling expenditure of the Supplier or the erection personnel.
5. The Purchaser shall attest to the hours worked by the erection personnel towards the Supplier at weekly intervals and the Purchaser
shall immediately confirm in written form if assembly, erection or commissioning has been completed.
6. If, after completion, the Supplier demands acceptance of the Supplies, the Purchaser shall comply therewith within a period of two
weeks. The same consequences as upon acceptance arise if and when the Purchaser lets the two-week period expire or the Supplies are
put to use after completion of agreed test phases, if any.
Article VII: Receiving Supplies
The Purchaser shall not refuse to receive Supplies due to minor defects.
XIMEA Technical Manual, Version: v240108
95
Содержание xiX-XL
Страница 18: ...Figure 8 Optical path cross section of MX1510 FF XIMEA Technical Manual Version v240108 11...
Страница 28: ...Figure 13 MX610xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 21...
Страница 30: ...Figure 15 MX610xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 23...
Страница 32: ...Figure 17 MX1018xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 25...
Страница 34: ...Figure 19 MX1018xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 27...
Страница 36: ...Figure 21 MX1510xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 29...
Страница 38: ...Figure 23 MX1510xR SY X4G3 FF with detached sensor sub assembly XIMEA Technical Manual Version v240108 31...
Страница 46: ...Digital input Wiring Figure 30 digital input interface wiring XIMEA Technical Manual Version v240108 39...
Страница 111: ...XIMEA GmbH Am Mittelhafen 16 48155 M nster Germany www ximea com Copyright XIMEA GmbH All rights reserved...