HEATING SYSTEM CONNECTION
6 720 641 467 (2010/01)
20
7.10 FILLING THE HEATING SYSTEM
After flushing the heating system the hot water heater
must be filled with water. The heating system is then
filled.
Fill the heating system:
1. Open the shut-off valve with non-return valve to fill
the DHW cylinder.
2. Open the valve to fill the system with heating water.
3. Open the air vent valve at the top of the DHW cylinder
to vent the heating system.
4. Also vent via the heat pump air vent valve.
5. Fill the heating system up to the correct pressure. The
standard pressure is 1-2 bar.
6. Shut the heating water filling cock when the correct
pressure is reached.
Fig. 20 Connection chamber, internal unit
1
Pressure gauge (0.5-1.5 bar)
Fig. 21 Heat pump
1
Air vent valve
WARNING:
The water heater can crack if
filling is performed in the wrong order.
B
Fill and pressurise the hot water heater
before
the heating system is filled.
1
6 720 641 935-07.1I
6 720 616 817-25.1I
1