Verify independent overspeed system
Commissioning Phase: Pre-operational checks
(Before applying fuel to system)
Wiring
Physical /
Mechanical
Installation
Verify fuel compatibility / quality
Turbine Control
Integration
Configure DVP for control system
Verify communications
Verify fault and diagnostic behavior (trip setting)
Demand and feedback loop check 0-100%
Visual check of correct valve movement
Verify internal shutdown operation and annunciation
Verify independent shutdown function and annunciation
Recommend demand is 0% at shutdown
Verify low demand signal noise
Verify voltage at DVP within limits during full valve step
Verify shutdown from safety system including overspeed
Document and archive DVP configuration settings
Commissioning Phase: Pre-start
(before turbine lightoff)
Wiring
Physical /
Mechanical
Installation
Verify no leaks
Turbine Control
Integration
Wet motor test recommended
Verify purge sequence operation
Flow rate verification (manifold pressure)
Verify internal shutdown operation and annunciation
Verify independent shutdown function and annunciation
Verify shutdown from safety system including overspeed
Commissioning Phase: Operational
Wiring
Physical /
Mechanical
Installation
Verify operating temperatures, Valve and DVP
Turbine Control
Integration
Verify fuel flow stability (manifold pressure)
Flow rate verification (manifold pressure and/or flow meter)
Verify transient performance
Verify low demand signal noise
Verify fuel schedule and emissions compliance
Released
Содержание Large Electric Sonic Valve II
Страница 14: ...Manual 35076 LESV II Woodward 12 Figure 1 1 Optional SIL2 Flow Sensor 3 4 6 inch LESV II Released...
Страница 15: ...Manual 35076 LESV II Woodward 13 Figure 1 2a Outline Drawing 2 Inch LESV II UHR SST 600 Dual Resolver Released...
Страница 16: ...Manual 35076 LESV II Woodward 14 Figure 1 2b Outline Drawing 2 Inch LESV II UHR SST 600 Dual Resolver Released...
Страница 17: ...Manual 35076 LESV II Woodward 15 Figure 1 3a Outline Drawing 3 Inch LESV II Class 600 Released...
Страница 18: ...Manual 35076 LESV II Woodward 16 Figure 1 3b Outline Drawing 3 Inch LESV II Class 600 Released...
Страница 19: ...Manual 35076 LESV II Woodward 17 Figure 1 4a Outline Drawing 4 Inch LESV II Class 600 Released...
Страница 20: ...Manual 35076 LESV II Woodward 18 Figure 1 4b Outline Drawing 4 Inch LESV II Class 600 Released...
Страница 21: ...Manual 35076 LESV II Woodward 19 Figure 1 5a Outline Drawing 6 Inch LESV II Class 600 Released...
Страница 22: ...Manual 35076 LESV II Woodward 20 Figure 1 5b Outline Drawing 6 Inch LESV II Class 600 Released...
Страница 40: ...Manual 35076 LESV II Woodward 38 Figure 3 11 Cable Motor Resolver 1 Feedback Signal Released...
Страница 41: ...Manual 35076 LESV II Woodward 39 Figure 3 12 Cable Stem Shaft Resolver LVDT Feedback Signal Released...
Страница 42: ...Manual 35076 LESV II Woodward 40 Figure 3 13 Cable Motor Resolver 2 Feedback Signal Released...
Страница 43: ...Manual 35076 LESV II Woodward 41 Figure 3 14 Cable Motor Power 2 Inch LESV II LELA1 with DVP5k Released...
Страница 63: ...Manual 35076 LESV II Woodward 61 Declarations Released...
Страница 64: ...Manual 35076 LESV II Woodward 62 Released...
Страница 65: ...Manual 35076 LESV II Woodward 63 Released...