제일 먼저 컨트롤판넬의 전원을 켠다. (First of all, turn on Control Panel) 

-

 레벨게이지 수면계의 수위가 절반이상 있는지 확인 한다. 물이 없다면 경고등이 켜져야 한다.

-

 소각로 급수 물탱크의 수위가 ⅔ 이상 있는지 확인 한다. 물이 없다면 경고등이 켜져야 한다.

-

 퇴출구 문을 열고 소각후 남은재를 전부 끌어낸다, 이때 하부 벽면, 노즐쪽에 굳은재는 최대한

긁어 낸다.

-

 레벨게이지/보일러 드레인 밸브를 열어 저수위 경고등, 부저가 작동할 때까지 물을 빼고,

보일러 저수위 경고가 정상 작동하는지 확인 하고, 

 다단펌프가 자동으로 작동하는지 확인 한다.

3

 Check if the water level is in more than two-thirds of Cyclone’s Water Supply Tank

 Check if the water level is in more than half. If there is no water, Warning Light will be turned on

 Open the door of ash outlet, rake out the remained ashes after burning.  At this moment, rake out

the hard ashes on the bottom of wall surface as much as possible.

 Please drain the water until the warning light and buzzer is operating by opening the drain V/V

from the level gauge and boiler. And check that the warning of low water level is properly operating.

 Check that Multistage Pump is operating automatically.

  2. 가동전 점검 사항(Check point before operation)

가동전 준비 사항(일일 점검 사항) Preparation before operation (Daily check)

블로우다운

 

Blow down 

Содержание WT-2500-4000

Страница 1: ...HEAD OFFICE FACTORY 22 NOKSANSANDAN 361 RO SONGJUNG DONG GANGSEO GU BUSAN KOREA TEL 82 51 831 0962 3 HOMEPAGE www perfectboiler co kr Separable Incineration Steam Boiler User s Manual...

Страница 2: ...2 3 4 5 6 7 1 8 A S 9 1 1 PVC 10...

Страница 3: ...ity of the problem caused by renovation of pipe and electronic devices without notice Be careful of burning body since the main body and pipes are running on a high temperature The operator should wea...

Страница 4: ...1 The name of each part 2 Check point before operation 3 How to use Control Panel 4 How to operate Boiler 5 How to inspect and clean 5 6 7 8 9 10 11 15 CONTENTS 1 2 3 4...

Страница 5: ...Ash Outlet Door 3 Level Guage Drain Valve 4 Boiler Drain Valve 5 Level Gauge Mcdonnell 6 Boiler Overheat Prevention Sensor 7 Waste Inlet Door 8 2 2nd Chamber Clean Door 9 2 2nd Combustion Chamber Ther...

Страница 6: ...SCRIPTION REMARK 15 Incinerator Water Supply Tank 16 Safety V V 17 SOLENOID V V Water Supply 18 Multistage Pump 19 Exhaust Fan 20 Chimney Clean Door 21 Cyclone Ash Clean Door 22 Pressure Switch 23 SOL...

Страница 7: ...e remained ashes after burning At this moment rake out the hard ashes on the bottom of wall surface as much as possible Please drain the water until the warning light and buzzer is operating by openin...

Страница 8: ...ing together 4 After draining the water from the incinerator please check that the water is properly supplied into the tank and the boiler compound is also put inside 2 Check point before operation Pr...

Страница 9: ...5 The display and the name of switch 3 How to use Control Panel 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25...

Страница 10: ...6 3 How to use Control Panel 1 2 3 ITEM NO DESCRIPTION REMARK 1 2 3 4 5 SOLENOID V V 6 OFF 7 8 A B 9 ON 10 ON 11 12 13 14 7 15 16 17 18 19 20 21 1 2 22 2 23 3 24 25 180...

Страница 11: ...nother when you repair or clean 9 Tower lamp on off switch Turn on while operating 10 Buzzer on off switch The alarm will be operated in case it is overheated and in low water level Turn on while oper...

Страница 12: ...e sure that you have put reasonable quantities inside and it has been buried in places because if you oversupply the waste will not get fire on the bottom So it is going be finished as incomplete comb...

Страница 13: ...the required steam pressure please slowly open the main steam valve In case of being the steam header please open the main steam valve on the top of boiler and control the valve of steam header 450 8...

Страница 14: ...e valve and blow down in the state of pressure dropped If the blower stops in the state which has not completely burned The combustion nozzle will be blocked it is possible to generate exhaust 4 How t...

Страница 15: ...weekly and inside combustion chamber the ashes from the surface of a wall When you clean the nozzle please use the driver and push to the end as below picture whether to check the holes are blocked or...

Страница 16: ...automatic injection device If not please fill in again When you drain while daily inspection please check more than once a week whether precipitate and solid are settled or not by filling the drained...

Страница 17: ...to the bottom and check there is scale 8 Since the boiler has been heated you have to drain after 8 hours later in the state of complete combustion Monthly check point 5 How to inspect and clean 13 L...

Страница 18: ...es in cyclone press stop button and supply water into the boiler by manual It is one of reason for the breakdown if you operate pump automatically without water in cyclone since the air comes into the...

Страница 19: ...boiler 15 Please open the front and back door Clean soot and dust on the pipe by using cleaning equipment which is provided At this time it is more effective if you use air compressor Monthly check po...

Отзывы: