PAGE 10
60706-186
7340-20
If only specific circuits are to be powered under emer-
gency power failure conditions, an additional distribution
panel designated “emergency distribution panel” must be
installed.
All selected emergency circuits are removed from main
distribution panels and reinstalled in the emergency
distribution panel. Suggested circuits: freezer, refrigera-
tor, furnace, emergency lights, sump pump, emergency
outlet circuits, etc. Total running load must not exceed
generator rating.
D.C. ELECTRICAL
INTERCONNECTION
*******CAUTION******
Never run the AC and DC wiring in the same conduit.
ASCO 165 UL SWITCH
Your DC connection points in the ASCO 165 UL ATS are
on the terminal block in the upper right hand corner of the
ATS panel. The terminal block (TB7) is numbered 1
through 9. These terminals will accept #22 - #14 stranded
wire. It is recommended that you use #16 for distances
up to 200 feet.
You will be using terminals 4 and 5, wire Start 23 will
connect to terminal #5 and wire Start 1 will connect to
terminal #4. See page 15 for a connection diagram.
ASCO 300 UL SWITCH
Your DC connection points in the ASCO UL ATS are
terminals “14” and “15” .Depending on the size of the
switch they are located in differnt locations. See below
INITIAL START UP
*************
***** WARNING *****
*************
DO NOT jump start these engine generator sets. Starting
these units on a low battery or jump starting them will
cause damage to the engine control module.
Use the following checklist to verify correct installa-
tion before starting the engine:
F
Engine oil.* Check level & fill as required with
proper grade/qty.
F
Unit mounting base properly bolted down.
F
Clearance for service and maintenance on all
sides.
F
Proper fuel line material and size.
F
All fuel line connections tight.
F
Fuel line protected and a moisture trap installed
(may be required for N.G.).
F
LP/NG pressure O.K. 4-6 Oz. (7-11" WC).
F
Battery connections clean and tight.
F
Battery fully charged.
F
All A.C. and D.C. wiring installed and properly
protected.
* Refer to engine owners manual for proper
levels and type.
After completing the above checklist, the engine generator
set is ready for the initial start-up test.
PROCEDURE
Move the selector switch on the engine generator to the
“RUN” position. The engine generator will crank and start
automatically. If the engine fails to start, return selector
switch to the “stop” position and correct the trouble before
proceeding.
With the engine running smoothly, check the no load
voltage and frequency at terminals L2 and L6 in the
ASCO ATS on the generator terminal block in the ATS.
The voltage should be between 242 to 248 volts. The
frequency should be between 61.5 to 62 hertz (Hz). The
voltage should also be checked between the hot terminals
(L2 and L6) and the neutral to be certain of a balanced
voltage output and a solid neutral connection. The
voltage should be about one half of the line to line voltage
or approximately 121 to 124 volts AC between both power
feeds and neutral.
** Notice **
If for any reason during the check out procedure the
voltage and frequency are not correct, turn the selector
switch to the “STOP” position and correct the trouble
before proceeding.
After verifying the voltage and frequency are correct, turn
the selector switch to the “STOP” position. The unit
should shut off with no time delay. You are now ready to
test the automatic start function.
Содержание PSS15B2W/D
Страница 1: ...PACKAGED STANDBY SYSTEM PSS15B2W D INSTALLATION AND OPERATORS MANUAL ...
Страница 10: ...PAGE 8 60706 186 7340 20 CUSTOMER AC AND DC CONNECTION POINTS TORQUE SPECIFICATIONS FOR CONNECTIONS ...
Страница 16: ...PAGE 14 60706 186 7340 20 AC AND DC GENERATOR WIRING DIAGRAM ...
Страница 18: ...PAGE 16 60706 186 7340 20 GENERATOR LAYOUT PSS15B4W ...