Commissioning
en
Installation and operating instructions Wilo-DrainLift SANI-M
21
7
Commissioning
WARNING
Foot injuries due to a lack of protective equipment!
Danger of (serious) injuries during work. Wear safety shoes!
NOTICE
Automatic activation after power cut
Depending on the process, the product is switched on and off using separate con-
trols. The product may automatically switch on following power cuts.
7.1
Personnel qualifications
ƒ
Electrical work: qualified electrician
Person with appropriate technical training, knowledge and experience who can
identify and prevent electrical hazards.
ƒ
Operation/control: Operating personnel, trained in the functioning of the complete
system
7.2
Operator responsibilities
ƒ
Providing installation and operating instructions by the lifting unit or at a place spe-
cially reserved for it.
ƒ
Making the installation and operating instructions available in the language of the
personnel.
ƒ
Making sure that the installation and operating instructions are read and understood
by all personnel.
ƒ
All safety devices and emergency cut-outs must be active and checked to ensure
that they function properly.
ƒ
The lifting unit is suitable for use under the specified operating conditions.
7.3
Operation
CAUTION
Malfunction due to incorrect operation of the switchgear!
When the plug is inserted, the switchgear starts in the last operating mode that was
set. In order to be familiar with the operation of the switchgear, the installation and
operating instructions for the switchgear must be read before inserting the plug.
The lifting unit is operated by the switchgear. The switchgear is pre-set for the lifting
unit. Read the installation and operating instructions for the switchgear to ensure it is
correctly operated:
ƒ
Settings
ƒ
LED displays/LC display
ƒ
Alarm signals
7.4
Test run
Carry out a test run before operating the lifting unit in automatic mode. A test run
checks the proper functioning and impermeability of the unit. It might be necessary to
adjust the pump’s follow-up time to guarantee optimum operation of the unit.
‡
Lifting unit installed properly.
‡
Connections to correct connection checked.
1. Activate the lifting unit: Insert plug into socket.
2. Select automatic mode on the switchgear.
3. Open the shut-off valve in the pressure pipe.
NOTICE! The shut-off valve in the inlet remains closed!
4. Unscrew the inspection cover on the collection reservoir.
5. Slowly fill the collection reservoir with water via the inspection opening with a
hose.
NOTICE! Malfunction! Do not hold water jet directly above the float switch!
6. Lifting unit is switched on and off using the level control.