4.4

Operating modes

Operating mode S3: Intermittent periodic duty

This operating mode defines a switching cycle in a combination of periods of operation
and standstill. Specified value (e.g. S3 25 %) relates to the operating time. The switch-
ing cycle has a duration of 10 min.
If two values (e.g. S3 25 %/120 s) are specified, the first value relates to the operating
time. The second value specifies the max. period of the switching cycle.

The unit is not designed for continuous duty! The max. volume flow applies to inter-
mittent periodic duty according to EN 60034-1!

4.5

Operation with frequency con-
verter

Operation on the frequency converter is not permitted.

4.6

Type key

Example: Wilo-DrainLift S 1/6M RV

DrainLift

Sewage lifting unit

S

Size

1

Single-pump system

6

Maximum delivery head in m at Q = 0

M

Mains connection version:
M = 1~230 V, 50 Hz
T = 3~400 V, 50 Hz

RV

Version with non-return valve

4.7

Technical data

Approved field of application

Max. intake per hour

600 l

Max. pressure in the pressure
pipe

1.5 bar

Max. delivery head

6 m

Max. volume flow

35 m³/h

Max. positive suction head

5 m

Fluid temperature

3...40 °C

Ambient temperature

3...40 °C

Motor data

Mains connection

1~230 V, 50 Hz

Power consumption [P

1

]

See rating plate

Rated power [P

2

]

See rating plate

Rated current [I

N

]

See rating plate

Speed [n]

See rating plate

Activation type

direct

Operating mode

S3 15 %/120 s

Protection class

IP68

Cable length to plug

1.4 m

Cable length to switchgear

4 m

Plug

Single-phase current: Shockproof plug
Three-phase current: CEE plug

Connections

Pressure connection

DN 80, PN 10

Inlet connection

1x DN 100, 2x DN 40

Ventilation connection

DN 70

Dimensions and weights

Gross volume

45 l

Switching volume

21 l

Содержание DrainLift S Series

Страница 1: ...Pioneering for You DrainLift S 2544878 Ed 02 2017 06 en Installation and operating instructions...

Страница 2: ......

Страница 3: ...ct description 9 4 1 Design 9 4 2 Monitoring devices 10 4 3 Operating principle 10 4 4 Operating modes 10 4 5 Operation with frequency converter 11 4 6 Type key 11 4 7 Technical data 11 4 8 Scope of d...

Страница 4: ...lities 23 9 3 Removal 23 9 4 Clean and disinfect 24 10 Maintenance and repair 24 10 1 Personnel qualifications 25 11 Spare parts 25 12 Disposal 25 12 1 Protective clothing 25 12 2 Information on the c...

Страница 5: ...ithin the warranty period Application according to intended use All monitoring devices are connected and tested before commissioning Exclusion from liability Exclusion from liability excludes all liab...

Страница 6: ...serious injuries CAUTION Failure to follow the instructions can lead to property damage and a possible total loss NOTE Useful information on handling the product Markups Prerequisite 1 Work step list...

Страница 7: ...s and on the rating plate Earth the device Switchgears are to be arranged overflow proof Replace defective power supply cables immediately Contact customer service 2 4 Monitoring devices The following...

Страница 8: ...ation Close the gate valve in the inlet and in the pressure pipe Provide adequate aeration in closed rooms When working in chambers and closed spaces a second person must be present for safety reasons...

Страница 9: ...xplosive fluids Pumping of highly flammable and explosive fluids gasoline kerosene etc in pure form is strictly prohibited There is a risk of fatal injury due to explosion The lifting unit is not desi...

Страница 10: ...nt for Pump OFF is defined by the set follow up time of the pump 4 1 4 Switchgear The lifting unit is controlled via the fitted switchgear The switchgear can also be used to implement a collective fau...

Страница 11: ...ainLift Sewage lifting unit S Size 1 Single pump system 6 Maximum delivery head in m at Q 0 M Mains connection version M 1 230 V 50 Hz T 3 400 V 50 Hz RV Version with non return valve 4 7 Technical da...

Страница 12: ...diately for defects damage completeness Defects must be noted on the freight documentation Furthermore de fects must be notified to the transport company or the manufacturer immediately on the day of...

Страница 13: ...t store the lifting unit in rooms in which welding work is carried out The resulting gases or radiation can corrode the elastomer parts The lifting unit must be protected from direct sunlight and heat...

Страница 14: ...te aeration of the operating space Ensure a clearance of min 60 cm around the system for maintenance work An additional pump sump in the operating space must be provided for draining large leakages mi...

Страница 15: ...ng and pipe adaptors and designed according to the requirements Pressure resistance of pipework and pipe adaptors Tensile strength of the pipe adaptors longitudinal force fit connection The following...

Страница 16: ...talled as a pipe loop The bottom edge of the pipe loop must be above the locally defined backflow level at its highest point Pressure pipe installed must be frost proof Install non return valve with v...

Страница 17: ...information when connecting the inlet pipe The inlet must be within the marked areas If the inlet is outside the marked areas the following problems can occur Connection on the collection reservoir wi...

Страница 18: ...n line over the roof Ensure all connections are completely tight Ventilation line is properly installed Installation materials available 1x pipe clamp 1 Open the connection port Pull the strip on the...

Страница 19: ...d sewage must be regularly pumped into the pressure pipe For this purpose it is recommended to install a diaphragm hand pump between the lifting unit and the pressure pipe Fig 8 Optional Diaphragm han...

Страница 20: ...chgear are shown in the circuit diagram in the appendix of these installation and operating instructions For further information on the individual functions observe the installation and operating inst...

Страница 21: ...gate valve in the inlet The lifting unit should no longer switch on because no more fluid flows in If the lifting unit switches on again the non return valve is leaky For correct functioning of the n...

Страница 22: ...accordance with local regulations Observe the specifications in the work regulations The operator must make sure that the personnel have received and read the work regulations 8 3 1 Overflow of the li...

Страница 23: ...regulations for working with and under suspended loads must be observed 9 3 Removal DANGER Danger due to fluids hazardous to health during removal During removal contact with fluids that are hazardou...

Страница 24: ...horing point 7 Pull the lifting unit carefully out of the pipework Lifting unit is dismantled Clean and disinfect the lifting unit and operating space 9 4 Clean and disinfect DANGER Danger due to flui...

Страница 25: ...ustomer service To avoid return queries and incorrect or ders the serial or article number must always be supplied Subject to change without prior notice 12 Disposal 12 1 Protective clothing Used prot...

Страница 26: ...0Hz 1 brown yellow green white grey blue brown black 2 3 4 5 L1 L2 L3 PE 3 400V 50 60Hz L1 L L2 N PE 1 230V 50 60Hz 1 230V 50Hz 30 15 0 Seconds ON 100 K DIP 1 2 3 4 5 6 7 PE SSM 1 2 3 7 8 9 4 5 6 GL W...

Страница 27: ......

Страница 28: ...Pioneering for You WILO SE Nortkirchenstr 100 44263 Dortmund Germany T 49 0 231 4102 0 T 49 0 231 4102 7363 wilo wilo com www wilo com...

Отзывы: