background image

36 

WILO SE 04/2014 V05 DIN A4

English

 

MAINTENANCE AND REPAIR

Any other work and/or alterations to the 

construction must only be carried out by Wilo 

customer service.

• 

When carrying out work in basins and/or tanks, 

the respective local protection measures must be 

observed in all cases. A second person must be 

present for safety reasons.

• 

Only lifting equipment that is in a technically 

perfect condition and load-carrying equipment 

that has been officially approved may be used for 

lowering and raising the pump. Make sure that the 

pump does not jam during lifting and lowering. 

If the pump does jam, no lifting forces greater 

than 1.2 times the pump weight must be applied. 

The maximum permissible bearing capacity must 

never be exceeded!

Make sure that the lifting gear, ropes and the 

lifting equipment's safety devices are in perfect 

working order. Work may only commence if 

the lifting equipment has been checked and 

found to be in perfect working order. If it is not 

inspected, fatal injuries may result.

• Electrical work on the pump and the system must 

be carried out by a qualified electrician. Defective 

fuses must be replaced immediately. They must 

never be repaired. Only fuses for the specified 

electric current and of the specified type may be 

used.

• 

If flammable solvents and cleaning agents are 

used, naked flames and smoking are prohibited.

• 

Pumps that circulate fluids that are hazardous to 

health or come into contact with such fluids must 

be decontaminated. In addition, make sure that 

no gases that are hazardous to health form or are 

present.

If injuries are caused by fluids or gases that 

are hazardous to health, apply the first-aid 

measures specified on the notice at the working 

premises and notify a doctor immediately.

• Make sure that the necessary tools and materials 

are available. Order and cleanliness ensure safe 

and smooth work on the pump. After working on 

the pump, remove any used cleaning materials 

and tools from the pump. Store all materials and 

tools in their proper place.

• 

Operating materials should be collected in suit

-

able containers and disposed of properly. Always 

wear appropriate protective clothing when per-

forming maintenance and repair work. This must 

also be disposed of properly.

8.1.  Operating materials

8.1.1.  Overview of white oil

The sealing chamber is filled with white oil that is 

potentially biodegradable.

When changing the oil, we recommend the fol

-

lowing oil types:

• 

Aral Autin PL*

• 

Shell ONDINA 919

• 

Esso MARCOL 52* or 82*

• 

BP WHITEMORE WOM 14*

• 

Texaco Pharmaceutical 30* or 40*

All oil types marked with “*” are approved for use 

with foods in accordance with “USDA-H1”.

Filling quantities

• 

TMT 32M113/7.5Ci: 900 ml

8.1.2.  Overview of grease

The following lubricating grease can be used in 

accordance with DIN 51818/NLGl Class 3:

• Esso Unirex N3

8.2.  Maintenance intervals

To ensure reliable operation, various maintenance 

tasks must be carried out regularly.

The maintenance intervals must be specified 

according to the load on the pump. Regardless of 

the specified maintenance intervals, the pump or 

installation must be checked if strong vibrations 

occur during operation.

When used in sewage lifting units inside 

buildings or on areas of land, the maintenance 

intervals and work shown in DIN EN 12056‐4 

must be adhered to.

8.2.1.  Intervals for normal operating conditions

2 years

• Visual inspection of the power supply cable

• Visual inspection of accessories

• Visual inspection of the coating and housing for 

wear

• 

Functional inspection of all safety and monitoring 

devices

• Inspection of the switchgear/relays used

• 

Oil change

15000 operating hours or after 10 years at the 

latest

• General overhaul

8.2.2.  Intervals for harsh operating conditions

Under harsh operating conditions, the specified 

maintenance intervals must be shortened accord-

ingly. In this case, contact Wilo customer service. 

If using the pump under harsh conditions, we also 

recommend signing a maintenance contract.

Harsh operating conditions include:

• 

A large proportion of fibrous material or sand in 

the fluid

• 

Turbulent inlet (e.g. due to air entry, cavitation)

• 

Strongly corrosive fluids

• 

Strongly gassing fluids

• Unfavourable duty points

• 

Operating states subject to water hammers

8.2.3.  Recommended maintenance measures to en-

sure smooth operation

We recommend regular inspections of the current 

consumption and the operating voltage in all 3 

phases. In normal operation, these values remain 

constant. Slight fluctuations depend on the char

-

acteristics of the fluid. The current consumption 

Содержание Drain TMT 32M

Страница 1: ... Betriebsanleitung en Installation and operating instructions fr Notice de montage et de mise en service tr Montaj ve kullanma kılavuzu pl Instrukcja montażu i obsługi cs Návod k montáži a obsluze ru Инструкция по монтажу и эксплуатации uk Iнструкція з монтажу та експлуатації ...

Страница 2: ...Fig 2 Fig 4 Fig 3 Fig 1 1 5 6 3 4 2 1 2 3 4 5 6a 6b Tmax 95 C Tmax 75 C W 5 1 2 V 4 U 3 M 3 gn ye L3 L2 21 20 L1 PE 250 V AC 2 5 A cos φ 1 6 DK 1 ...

Страница 3: ...pe of delivery 28 3 7 Accessories 28 4 Transport and storage 28 4 1 Delivery 28 4 2 Transport 28 4 3 Storage 29 4 4 Return delivery 29 5 Installation 29 5 1 General 29 5 2 Installation methods 29 5 3 Installation 30 5 4 Dry running protection 31 5 5 Electrical connection 32 5 6 Motor protection and activation types 33 6 Commissioning 33 6 1 Electrical system 33 6 2 Rotation control 33 6 3 Level co...

Страница 4: ...o make technical modifications to units or components This operating and maintenance manual refers to the pump shown on the title page 1 5 Warranty In general the specifications in the current gen eral terms and conditions apply for the warranty You can find these here www wilo com legal Any deviations must be contractually agreed and shall then be given priority 1 5 1 General The manufacturer is ...

Страница 5: ... When installing or removing the pump never work alone in rooms and sump A second person must always be present The pump must always be switched off before any work is performed on it assembly disman tling maintenance installation The pump must be disconnected from the electrical system and secured against being switched on again All rotating parts must have come to a stop The operator should info...

Страница 6: ... 2 4 Safety and monitoring devices The pumps are equipped with a thermal winding monitor and leakage connection for the motor The pump is switched off if the motor gets too hot during operation or if liquid gets into the motor These devices must be connected by an electri cian and checked to ensure that they function correctly before commissioning Personnel must be informed about the installed sys...

Страница 7: ...ational regulations DANGER explosive fluids It is strictly prohibited to pump explosive flu ids gasoline kerosene etc The pumps are not designed for these fluids The Wilo Drain TMT 32M submersible pumps are designed for intermittent and permanent pump ing of wastewater with solids up to a maximum of 9 mm in sumps and tanks The submersible pumps must not be used for pumping Potable water Fluids con...

Страница 8: ... 20 h Maximum 50 h Cable Type TGSH J Size 7G1 5 Length 10 m Fluid temperature T Immersed 3 95 C 37 203 F Non immersed 3 75 C 37 167 F 3 5 Type key Example Wilo Drain TMT 32M113 7 5Ci TM Tauchmotorpumpe submersible pump T Pumping of wastewater 32 Pressure connection G 1 DN 32 M Half open multi channel impeller 113 Impeller diameter in mm 7 5 10 rated power P2 in kW Ci Material version Cast iron 3 6...

Страница 9: ...oating fulfils its intended purpose Please note that elastomer parts and coatings become brittle over time If the product is to be stored for longer than 6 months we recommend checking these parts and replacing them as nec essary Consult the manufacturer for details 4 4 Return delivery Pumps that are returned to the factory must be properly packaged This means that impurities have been removed fro...

Страница 10: ...s stability and strength If the motor housing is to be taken out of the fluid during operation the operating mode for non immersed operation should be followed To keep dry motors sufficiently cooled in S3 mode they must be flooded completely before being switched back on if the motor has been taken out of the fluid Never let the pump run dry The water level must never fall below the minimum Theref...

Страница 11: ...nstallation location If neces sary secure lifting equipment to the pump with a shackle lift the pump and then lower to the intended location sump pit Check that the pump is vertical and on a solid bearing surface Avoid sinking Route the power supply cable so it cannot be damaged Have the electrical connections made by a qualified electrician Route the pressure hose so that it is not damaged and fa...

Страница 12: ...ice RCD Switchgears must be purchased as accessories 5 5 1 Mains fuses The back up fuse must be rated according to the starting current You will find the starting current on the rating plate Only slow blow fuses or K characteristic auto matic cut outs may be used as a back up fuse 5 5 2 Checking the insulation resistance and moni toring devices before commissioning If the values measured deviate f...

Страница 13: ...ating mode Minimum water submersion max immersion depth These general conditions must also be checked after a lengthy period without operation and any defects detected must be repaired Always keep this manual either by the pump or in a place specially reserved for it where it is accessible for the entire operating personnel at all times In order to prevent damage or serious injury when commissioni...

Страница 14: ...ecked for wet well installation Clean the pump sump of coarse contaminants Open all slide valves on the pressure side 6 4 2 Switching on off The pump is switched on and off using a sepa rate operating point on off switch switchgear provided by the customer During the start up procedure the rated current is temporarily exceeded After the start up pro cedure is finished the current must not exceed t...

Страница 15: ...uitable lifting device may be required to do this 7 4 Return delivery storage For shipping the parts must be packed in tear proof plastic bags of sufficient size in such a manner that they are tightly sealed and leak proof For return delivery and storage please also refer to the Transport and storage section 7 5 Disposal 7 5 1 Operating materials Oils and lubricants must be collected in appropri a...

Страница 16: ... per forming maintenance and repair work This must also be disposed of properly 8 1 Operating materials 8 1 1 Overview of white oil The sealing chamber is filled with white oil that is potentially biodegradable When changing the oil we recommend the fol lowing oil types Aral Autin PL Shell ONDINA 919 Esso MARCOL 52 or 82 BP WHITEMORE WOM 14 Texaco Pharmaceutical 30 or 40 All oil types marked with ...

Страница 17: ...for the monitoring equip ment has to be disconnected in the switchgear The monitoring equipment can then be checked with an ohmmeter The following values should be measured Bimetallic strip Value 0 passage If there are larger deviations consult the manu facturer 8 3 5 Inspection of the switchgear relays used See the relevant installation and operating in structions for a description of the individ...

Страница 18: ... fluid available Open inlet for tank or slide valve 2 Intake blocked Clean the supply line slide valve suction piece suction port or suction strainer 3 Impeller blocked or slowed Switch off pump secure it against being switched back on again and free the impeller 4 Faulty hose piping Replace defective parts 5 Intermittent operation Check switching system Fault The unit runs but not within the spec...

Страница 19: ...mer Service On site support from Wilo customer service Inspection or repair of the pump at the factory Please note that you may be charged for some services provided by our customer service For more details please contact Wilo customer service 10 Appendix 10 1 Spare parts Spare parts can be ordered from Wilo customer service To avoid return queries and incorrect or ders the serial and or article n...