background image

7

Part Number 550-110-739/0703

GSA

 

Gas-Fired Steam Boilers – 

User’s Information Manual

  Check monthly

Boiler relief valve

1. After following the warning directions

below, if the relief valve weeps or will
not seat properly, replace the relief valve.

Before testing, make certain
discharge pipe is properly

connected to valve outlet and arranged to
contain and safely dispose of boiler
discharge. Wear gloves to protect your
hands from hot surfaces. Verify that
discharge piping is installed in accordance with this manual and
the instructions on the relief valve tag. Failure to comply will expose
operator and others to severe personal injury or death.

Safety relief valves should be reinspected AT LEAST
ONCE EVERY THREE YEARS, by a licensed

plumbing contractor or authorized inspection agency, to ensure that
the product has not been affected by corrosive water conditions
and to ensure that the valve and discharge line have not been altered
or tampered with illegally. Certain naturally occurring conditions may
corrode the valve or its components over time, rendering the valve
inoperative. Such conditions are not detectable unless the valve
and its components are physically removed and inspected. This
inspection must only be conducted by a  plumbing contractor or
authorized inspection agency — not by the owner. Failure to
reinspect the boiler relief valve as directed could result in unsafe
pressure buildup, which can result in severe personal injury, death
or substantial property damage.

Check the setting of the boiler limit control. The
control should never be set with a pressure above

10 psig. Operating at a higher pressure can cause damage to the
boiler relief valve.

The boiler relief valve must be tested at least
monthly during the heating season to verify the valve

and discharge piping flow freely. If corrosion and/or deposits are
noticed within the valve body, testing must be performed more often.
A “try lever test” must also be performed at the end of any non-
service period. Follow the instructions below for a “try lever test”.

With the system at operating pressure, lift and hold the test
lever fully open for at least 5 seconds to flush the valve seat
free of sediment and debris. Then release lever and permit the
valve to snap shut.

Pilot burner flame

Proper pilot flame (see right):

1. Blue flame.

2. Inner cone engulfing

thermocouple.

3. Thermocouple glowing

cherry red.

Improper pilot flame:

1. Overfired — Large flame

lifting or blowing past
thermocouple.

2. Underfired — Small flame. Inner cone not engulfing

thermocouple.

3. Lack of primary air — Yellow flame tip.

4. Incorrectly heated thermocouple.

Main burner flame

Proper main burner flame
(see right):

1. Yellow-orange streaks may

appear (caused by dust).

Improper main burner flame:

1. Overfired — Large flames.

2. Underfired — Small flames.

3. Lack of primary air — Yellow tipping on flames (sooting will

occur).

  Check monthly

  Periodically

Test low water cutoff

Probe-type low water cutoff
(see right)

Check probe-type low water
cutoff for proper operation.

1. Turn off power to boiler and

wait 5 minutes.

2. Drain water to bottom of

gauge glass.

3. Turn on power.

4. Set thermostat to call for

heat. Red neon lamp on
lower water cutoff should light.

5. Wait 5 minutes. Boiler should not fire.

6. Refill boiler to correct water line. Red lamp should go off.

7. Wait 5 minutes. Boiler should fire.

8. Return thermostat to normal setting.

Float-type low water cutoff (by others, if used)

1. Blowdown control  and test per control manufacturer’s

instructions.

Scald potential. Do not blowdown low water cutoff
unless blowdown piping has been installed according

to control manufacturer’s instructions. If piping is not installed, call
a qualified service technician.

Содержание RVGP

Страница 1: ...e gas odorant Propane boilers only Your propane supplier mixes an odorant with the propane to make its pres ence detectable In some instances the odorant can fade and the gas may no longer have an odo...

Страница 2: ...5 Should overheating occur or gas supply fail to shut off do not turn off or disconnect electrical supply to pump Instead shut off the gas supply at a location external to the appliance 6 DO NOT use t...

Страница 3: ...75 through GSA 250 4 Robertshaw 7200 GSA 075 through GSA 175 5 Service technician covered in Boiler Manual for use only by a qualified service technician Owner maintenance see pages 6 8 for instructio...

Страница 4: ...to the appliance 5 When equipped with Johnson Controls vent damper Model M35 manually rotate damper blade in direction of arrow to Open position indicated on damper assembly 6 Turn gas control knob cl...

Страница 5: ...n to inspect the appliance and to replace any part of the control system and any gas control which has been under water 1 Stop Read the safety information above on this label 2 Set the thermostat to l...

Страница 6: ...ing section failure Do not use petroleum based cleaning or sealing compounds in boiler system Severe damage to boiler and system components can occur resulting in possible severe personal injury death...

Страница 7: ...g the heating season to verify the valve and discharge piping flow freely If corrosion and or deposits are noticed within the valve body testing must be performed more often A try lever test must also...

Страница 8: ...ant use of makeup water Call qualified service technician to de lime boiler if necessary In some cases deposits will be too heavy to remove with de liming procedures Have qualified service technician...