Commissioning
6.1 Safety during commissioning
6
6
Commissioning
6.1
Safety during commissioning
•
Ensure that the machine is only commissioned by qualified personnel in compliance
with the safety instructions.
•
Ensure that only authorised personnel are in the work area, and that no one could be
injured due to the commissioning process.
The following prerequisites must be met prior to commissioning the machine:
•
The machine is correctly mounted.
•
The electrical equipment for the power supply is available and correctly fitted.
•
All cables are laid properly and correctly connected in compliance with valid electrical
circuit documents.
•
The shielding of the motor wires is in place.
•
The static discharge must be conducted properly.
The shunt resistance must be measured and have a value of < 10 MOhm.
The measurement must be recorded in a log.
•
The required safety equipment and emergency stop circuits are available and
functioning correctly.
Prior to commissioning the machine, check whether
•
the drive is undamaged and not blocked.
•
all connections have been correctly established.
•
all safety covers are correctly installed.
•
no other hazard sources are present.
•
no foreign materials, tools or other objects are lying in the operating area of the
machine.
The following should be checked during commissioning
•
the axles are running properly.
Jerking of the axles may indicate incorrect control parameters.
•
no excessive noise development is detected.
A strong development of noise may indicate improper assembly or incorrect con-
trol parameters.
Injuries emanating from unexpected activation.
Incorrectly-established connections or external influences on electrical equipment can
cause unexpected activation of the machine or uncontrolled movement. Ensure that
nobody is present in the hazardous zone around the machine. Activate and check all
safety equipment and emergency stop circuits prior to commissioning.