1.
The
DEMAND
LED status indicator will light.
2.
The unit checks to ensure that the Proof of Closure (POC) switch in the downstream
Safety Shut-Off Valve (SSOV) is closed. See Figure 3-3 for SSOV location.
Figure 3-3:
BMK 750/1000:
SSOV Location
3.
With all required safety device switches closed, a purge cycle will be initiated and the
following events will occur:
a. The Blower relay energizes and turns on the blower.
b. The Air/Fuel Valve rotates to the full-open purge position and closes purge position
switch. The dial on the Air/Fuel Valve (Figure 3-4) will read
100
to indicate that it is
full-open (100%).
c. The
VALVE POSITION
bargraph will show 100%.
NATURAL GAS INLET
TO
AIR/FUEL
VALVE
MANUAL SHUT-OFF
VALVE
LOW GAS
PRESSURE SWITCH
HIGH GAS PRESSURE
SWITCH
SSOV