7 Quick-start procedure
Before switching on the hydraulic unit :
• Check the electric wiring.
• Check the refrigeration circuit and make sure the gas
supply has been performed.
• Check the pressure of the hydraulic circuit (1-2 bar),
check that the heat pump is purged, and the rest of the
installation.
• Make sure that ALL DIP SW are OFF before starting
up. (figure
23 page 20
).
7 1 Start-up check-list
7 1 1 Before starting-up
•
Sight checks
Outdoor unit (see chapiter "Installation of the outdoor unit"
page 12
)
OK
Non compliant
Location and fittings, condensate evacuation.
Compliance with distances from obstacles.
•
Hydraulic checks
Hydraulic unit (see chapiter "Installing the hydraulic unit"
page 15
)
OK
Non compliant
Value
Connection of pipes, valves and pumps (1 or 2 circuits, DHW).
Installation water volume (expansion vessel of adequate capacity ?).
No leaks.
Main system pressure and degassing (0,3bar > expansion vessel pre-loading).
•
Refrigeration connections and checks
(see chapiters "Refrigeration connections"
page 16
and "filling the installation with gas"
page 19
)
OK
Non compliant
Refrigerant circuits control (Sealing respected, no dust and moisture)
Connections between units (pipe length, flare tightening torque...).
Installation of HP, LP pressure switches on "Gas" line (large pipe).
Pump down required.
Nitrogen leak test (~ 25 bar).
Refrigerant filling of hydraulic unit and pipes.
Opening of refrigeration valves to outdoor unit.
•
Electrical checks
Outdoor unit (see chapiter "Electrical connections"
page 22
)
OK
Non compliant
Value
Main power supply 400v .
Protection by rated circuit breaker.
Cable cross-section.
Earth connection.
Hydraulic unit (see chapiter "Electrical connections on the hydraulic unit side"
page 25
)
OK
Non compliant
Connection with outdoor unit (3 + Eath).
Sensors connection (positioning and connections).
3 way valve and circulators connections.
Power supply and protection of electric auxiliary.
Installation and operating manual "1364 - EN"
- 57 -
Split system (3-phase)