3.6 ADJUSTMENT OF PILOT
Note to Gasfitters
The 3 flame pilot may need adjustment after a period of running time on set up as the increase in heat in the fire will induce a higher
draught in the fire, and may pull in flame away from the file tube causing the fire to shut down.
When the base screw is removed, gas will leak from the outlet. Ensure that the pilot is not adjusted or the screw is removed when the fire
is burning.
•
Adjustment of pilot
-
3 Flame: Unscrew base screw as shown in Diagram 2.
•
Insert a screwdriver as shown in Diagram 3 and adjust the adjustment screw up inside the 3 Flame Pilot to adjust the flame height.
•
The flame must always be passing over the electrodes &/or file tube on either side.
•
Replace the base screw and check for leaks.
Correct operation of 3 Flame Pilot
3 Flame Pilot in
3.7 COMMISIONING AND TESTING
Read all the instructions before commissioning. Install coals and logs and burner before commission.
Light appliance and check HIGH/LOW settings. Check operation of appliance and adjust to suit.
Adjust control valve setting if required. After a period of running (30min plus) check the setting of the pilot and adjust if required. See
specs for details.
Extinguish appliance, remove test equipment and secure test nipple. Check for gas leaks.
Note: The control valves are factory set and should not require adjustment.
Gasfitter to carry out standard testing for commission:
•
Spill test taken at top of opening with smoke or smoke match
•
Leak testing appliance and joints
•
Correct operation of the burner and coal and log lay out
•
Test gas pressures high and low, drop test on supply line
•
5 second light time across burner, Other testing that may be required
•
Ventilation requirements to the standards
•
Clean and or touch up paint of fire box and burner
•
Hand over to client, tests to comply to relevant standards