Petring Energietechnik GmbH – Paderborner Str. 76 – 33189 Schlangen
Tel: +49 5252 989440 Mail: [email protected]
23
4.1 Technical details: Electrical connection-conditions
Electrical connection-conditions
Model
wallb-e eco 2.0
3,7kW
wallb-e eco 2.0
4,6kW
wallb-e eco 2.0
7,4kW
wallb-e eco 2.0
11kW
wallb-e eco 2.0
22kW
Input terminal
X1
L1/N/PE
X1
L1/N/PE
X1
L1/N/PE
X1
L1/L2/L3/N/PE
X1
L1/L2/L3/N/PE
Supply line
NYM-J
3x2,5mm²
NYM-J
3x2,5mm²
NYM-J
3x6mm²
NYM-J
5x2,5mm²
NYM-J
5x6mm²
LS_switch/
preliminary fuse
1 pol. x C 16A
1 pol. x C 20A
1 pol. x C 32A
3 pol. x C 16A
3 pol. x C 32A
RCD
Fi Typ A or
Typ A (EV)
0,03A/25A
Fi Typ A or
Typ A (EV)
0,03A/25A
Fi Typ A or
Typ A (EV)
0,03A/40A
Fi Typ A (EV)
0,03A/40A
Fi Typ A (EV)
0,03A/40A
6.
Be aware
that you have to install an adequate LS-switch (see table) in the
subdistribution!
7.
Be aware
that you have to integrate an RCD (see table) in the sub distribution if you
are installing one of the following wallb-e eco 2.0 versions:
11kW
and
22kW
.
8.
wallb-e eco 2.0 with charging cable Type 1 or Type 2.
a.
Only the 3,7kW, 4,6kW and 7,4kW variants feature an integrated RCD.
9.
wallb-e eco 2.0 with Type 2 socket:
a.
Only the 3,7kW and 4,6kW version feature an integrated RCD.
10.
We strongly advise you to follow local norms and regulations.
11.
We strongly recommend:
Residual Current Operated Devices (RCD’s) “Every connection point needs to be
protected with its own residual current operated device (RCD) with a calculation
difference stream, which shouldn’t be more than 30mA. The selected residual
current operated device (RCD) needs to turn off all active wires including the neutral
wire. The connection point of the selected residual current operated device (RCD)
should be at least a Type A. If the characteristic of the charging performance is not
known, referring to the possible DC fault currents of more than 6mA, protection
measures need to be taken if DC fault currents appear, e.g. using a residual current
operated device (RCD) Type B or Type A (EV).”
Questions: +49-5252-989440
The installation, connection and initial start-up must be performed by trained
personnel with corresponding abilities.