Installation & Start-up – HES Series
6
FIGURES 2 and 3 illustrate two methods of lifting & setting Tube-Ice
®
machine on a ice storage bin.
! CAUTION !
The approximate weight of the machine is 1360 pounds.
Always use equipment with adequate load-carrying capacity.
! CAUTION !
FIGURE - 2
Forklift-&-Blocks Method
You need: +
forklift truck with adequate load and height capacities
+
(8) 2X4 wood blocks 8 in. long
+
(2) wooden 2X4’s measuring 3-ft. long
+
pry bar
Step 1.
Position Tube-Ice
®
machine on forks.
! CAUTION !
The Tube-Ice
®
machine may be somewhat top heavy on the rear.
! CAUTION !
Step 2.
Stack wood blocks in each corner of the drip pan on top of the ice storage bin.
Step 3.
Lift and set Tube-Ice
®
machine on wood blocks.
Step 4.
Remove forklift.
Step 5.
Stack 3-ft. long 2X4’s beside drip pan, overlapping front and back of bin.
Step 6.
Using a pry bar with fulcrum on 2X4’s, raise side of machine enough to remove TOP
wood blocks.
! CAUTION !
Do not remove top AND bottom blocks at the same time.
! CAUTION !
Step 7.
Repeat steps 5 and 6 on other side.
Step 8.
With machine sitting on one (1) block under each corner, repeat steps 5, 6, and 7 remove
remaining blocks. Drip pan flanges may bend slightly.
Step 9.
Straighten bent drip pan flanges.
Step 10. Check alignment of ice chute to bin opening.
Содержание HE S Series
Страница 1: ...5 2 2011 HE S Series TUBE ICE MACHINE INSTALLATION START UP INSTRUCTIONS Part Number 12A4171S0702 ...
Страница 2: ...Installation Start up HES Series 2 Blank Page ...
Страница 12: ...Installation Start up HES Series 12 FIGURE 8 Typical Space Diagram ...
Страница 26: ...Installation Start up HES Series 26 FIGURE 16 Piping Schematic Air Cooled ...
Страница 27: ...Installation Start up HES Series 27 FIGURE 17 Piping Schematic Water Cooled ...
Страница 41: ...Installation Start up HES Series 41 Casing Installation FIGURE 28 Stainless Casing Installation ...