10
5.3.1
Boiler drum installation
1.
Put the boiler drum on an embedding
2.
Put a sealing
φ
90 x 60 x 3 on the upper flange part of the back section and fix the flange of the heat water. The flange to be welded to the
distribution of the heat water in advance.
3.
Put a sealing
φ
90 x 60 x 3 on the bottom flange part of the back section and fix the flange of the returnable water with a socket for
impregnating and clearing plug. The flange to be welded to the distribution of the returnable water in advance.
4.
An elbow with an impregnating and clearing plug to be screwed to the flange socket of the returnable water after connection of the boiler to
the heat system.
5.
Screw the well of thermostat into the hole in the top part of the rear section.
Fig.
№
. 7
6.
To put the stove – pipe to the smoky chimney - pot and penetrate it into the chimney hole
7.
To screw the draught controller to the hole in the upper part of the front section
8.
Two holes with a Js 6/4“ thread in the front section to blind with Js 6/4“ closures
Fig.
№
. 8
The boiler connecting dimensions
5.3.2
Jacket assembly
1.
Take the jacket off the cardboard packing
2.
To sink the jacket side parts with an enclosed connecting material and fix it with brackets according to the Fig.
№
. 9.
3.
To unloose the bottom anchor screws and put on the side jacket brackets. Insert the front brackets between the backings with nuts and
front section body, the back brackets to be inserted directly to anchor screws.
Fig.
№
. 9
Jacket side part
Fig.
№
. 10
Smoky flap control
1
Check valve for the manometer
2
Well of thermostat