Turning on the hardware and verifying operation
The hardware components must be turned on in a specific sequence to ensure
correct communication between them.
To turn on the components and verify operation
1
Check and verify that the following cables are connected properly and securely:
■
Data and network cables on the compute node
■
Fiber Channel (FC) cables between the compute node and the Primary
Storage Shelf
■
Power cords from each component to the appropriate Power Distribution
Unit (PDU) in the rack
2
On the rear of the Primary Storage Shelf, turn on both power switches.
3
Verify that the left-most LEDs on both power canisters are green.
45
Installation procedures
Turning on the hardware and verifying operation