3

Install one CT (must be on phase  A current connection) and
connect all three voltage leads to A,B, and C voltage
connections.  Current inputs B and C should be jumpered
(see drawing below). If this option is selected, the calcula-
tions for kW demand are as follows:

kW DEMAND = E  x  

 I

  x  1.73  x  (mA out -4)  x 2

1000  x 16

Install 1 CT on the "hot" lead per the installation instruc-
tions (i.e., arrows facing the load) and connect the leads
from the CT to phase A current input.  Connect the voltage
input from the "hot" lead to phase A voltage input and the
voltage from the neutral to the phase B voltage input.
Current inputs B and C should be jumpered. If this method
is used, the calculation for kW demand is as follows:

     SINGLE PHASE VOLTAGE WITH A NEUTRAL

(e.g., 120 V), the following installation instructions
apply 

(see drawing below)

:

SINGLE PHASE INSTALLATION ON THREE-PHASE
BALANCED LOADS

kW DEMAND = E  x 

 I

  x  1.73  x  (mA out -4)  x 3

1000 x 16

FORMULA DESIGNATIONS

     240V, 3 WIRE, SINGLE PHASE

Hot

N

Hot

WHT
BLK

WHT
BLK

ØB

WHT
BLK

ØC

Required shorting links

LINE

ØA

LOAD

ØB

L-2

ØC

L-3

ØA

L-1

FUSE

FUSE

FUSE

L-1

L-2

L-3

FUSES: 600 V 1/4 AMP, 100 KAIC

Hot

WHT
BLK

WHT
BLK

ØB

WHT
BLK

ØC

Required shorting links

LINE

N

ØA

LOAD

ØB

L-2

ØC

L-3

ØA

L-1

FUSE

FUSE

FUSE

L-1

L-2

L-3

FUSES: 600 V 1/4 AMP, 100 KAIC

120V (example)

Voltage

Select Switch

240V (example)

Voltage

Select Switch

kW DEMAND = E  x 

 I

  x  1.73  x  (mA out -4)

1000   x 16

WHT
BLK

WHT
BLK

ØB

WHT
BLK

ØC

Required shorting links

LINE

ØA

LOAD

ØB

L-2

ØC

L-3

ØA

L-1

FUSE

FUSE

FUSE

L-1

L-2

L-3

FUSES: 600 V 1/4 AMP, 100 KAIC

E = Line to Line Voltage

 I

 = Maximum rated full-scale of one CT in amps

mA out =  4 to 20 mA reading (supply DC source)

Содержание H-6001

Страница 1: ...each phase to calculate true RMS power KW ExIx1 73xpowerfactor Theinstantaneous power KW of all three phases is summed and converted to an industry standard 4 20 mA output signal for use in demand ma...

Страница 2: ...G DIAGRAM This unit accepts 1 0V full scale output Current Transformers CTs only Do not use 0 5A OUTPUT Current Transformers e g 200 5 type CTs without H 6902B Adapter Consult Factory Enclose unit by...

Страница 3: ...WITH A NEUTRAL e g 120 V the following installation instructions apply see drawing below SINGLE PHASE INSTALLATION ON THREE PHASE BALANCED LOADS kW DEMAND E x I x 1 73 x mA out 4 x 3 1000 x 16 FORMUL...

Страница 4: ...sensors to be used in parallel so that multiple locations can be monitored by a single meter This allows for a totalized output from two or more locations RULES FOR ACCURATE PARALLEL INSTALLATION 1 Cu...

Страница 5: ...y voltage divided by secondary voltage Locate transducer within 30 of current transformers in an area accessible to qualified service personnel only Transducer and or enclosure should be mounted using...

Страница 6: ...L 3 to ensure phases are not reversed and that all are connected B Check that voltages on phases are above undervoltage set point Problem Pulse LED does not blink Solution A Ensure monitored load is...

Страница 7: ...9 0 0040 0 0100 0 0140 0 0200 0 0300 0 0400 0 0600 0 0800 0 1200 0 1600 0 2000 0 6 1 7 0 0080 0 0200 0 0280 0 0400 0 0600 0 0800 0 1200 0 1600 0 2400 0 3200 0 4000 0 3 3 5 0 0160 0 0400 0 0560 0 0800...

Страница 8: ...kside of the LCD display The front red push button may be enabled or disabled with the jumper When disabled the display may only be reset using the black reset switch near the jumper This feature is u...

Отзывы: