Start up
General Instructions
transforma
.plur: Transformers with corrugated tank
and submerged in dielectric liquid from 3150 kVA
5.
Keep the transformer supplied with no-load for at least
12 hours, checking that there are no anomalies in any of
the transformer instruments.
6.
Progressively apply the load until the operating power
is achieved, while ensuring that the transformer
temperature does not go over 105 °C. In the case of
renewable generation transformers, connect to the
generation source in low generation conditions and let
it increase naturally.
Risk of death caused by electric shock and of
irreversible damage to the transformer or to the
electrical installation.
• Before handling the installation, exactly follow the
instructions of Section 6.1 of this general instructions
document.
• Do not operate the tap changer with no load with
electrical power applied to the transformer.