4.1

STARTUP PROCEDURE

NOTE

Caution  should  be  exercised  when  applying 
this  and  any  electronic  device  to  explosive 
vapor extraction and measurement applications.  
Typical  hazards  in  these  applications  include 
small  fitting  vapor  leaks,  resulting  in  dangerous 
gas  concentrations  near  or  within  the  system 
enclosure.  Any spark or arc may result in a fire 
or explosion in these conditions.  Always inspect 
all fittings for leakage before commissioning, and 
always remove power from all electronic devices 
before  performing  maintenance  on  the  vapor 
extraction system tubing, fittings, and hardware.

1.   Inhibit  the  output  loads  that  are  actuated  by  the 

system to prevent activation of these devices.

2.   Check that the PIRVOL has been wired properly.

3.   Apply power to the system and allow the PIRVOL 

to  operate  for  a  minimum  of  2  hours,  then  check 
zero and verify gas response.

4.   Place  the  system  in  normal  operation  by 

reactivating the output loads.

TROUBLESHOOTING

Refer  to  Table  2  to  isolate  and  correct  malfunctions 
with the PIRVOL.

MAINTENANCE

It is recommended to have spare IR Modules on hand 
(see “Spare Parts” section).  Use Table 2 to isolate and 
correct malfunctions.

IMPORTANT MAINTENANCE NOTES

•  Hydrocarbon-based  grease  emits  hydrocarbon 
vapors,  which  will  be  measured  by  PIRVOL, 
resulting in elevated gas concentration readings.  

Use  only  silicone -based  grease  (not 
hydrocarbon-based grease) when lubricating 
threads  on  the  PIRVOL  and  associated 
junction box.  

A suitable grease is listed under 

“Spare Parts” in the Ordering Information section 
of this manual.  

•  It  is  recommended  to  keep  spare  IR  modules 
(See “Spare Parts” section) for field replacement 
in the event of a malfunction.

9

95-8522

  Current Level 

Status 

Corrective action

  2.4 to 3.9 ma 

Negative Zero Indication 

NOTE:  

This fault can be caused by the presence of background gas

 

 

 

during  calibration.    Ensure  that  background  gas  is  not  present  and 
recalibrate  the  unit.    If  fault  does  not  clear,  perform  disassembly 
and cleaning procedure, then recalibrate.  If fault still does not clear, 
replace electronics assembly.

 

1.6 ma 

Calibration fault 

Make  sure  that  the  calibration  gas  being  used  matches  the  Gas 
Selection Switch setting.  If these match and the fault is still present, 
perform disassembly and cleaning procedure, then recalibrate.  

 

1.0 ma 

Fouled optics 

Perform disassembly and cleaning procedure, then recalibrate.  

 

0.8 ma 

+24 vdc line low (less than +17.5 vdc) 

Ensure  that  input  voltage  is  correct  and  that  power  connections  are 
good.  If fault does not clear, replace the electronics assembly.

 

0.6 ma 

Calibrate input active at power-up 

Ensure  that  calibration  line  is  not  shorted  and  that  the  calibration 
switch is open.  If fault does not clear, replace the unit.

 

0.4 ma 

Active channel fault 

Replace electronics assembly.

 

0.2 ma 

Reference channel fault 

Replace electronics assembly.

 

0.0 ma 

CPU system fault, warmup 

Ensure that power is applied and that the warmup period is complete 
(1 minute).  If fault does not clear, replace the unit.

Table 2—Troubleshooting Table

Содержание DET-TRONICS 95-8522

Страница 1: ...Instructions 95 8522 Volumetric IR Process Gas Monitor PIRVOL Series 4 1 7 07 95 8522 ...

Страница 2: ...ay Device 5 Operating Modes 5 Installation 6 Device Mounting Orientation 6 Junction Boxes 6 General Wiring Requirements 6 Wiring Procedure 7 Detector Separation Optional 8 Startup Procedure 9 troubleshooting 9 Maintenance 9 Disassembly and Cleaning Procedure 10 Calibration 11 Device Repair and Return 12 Ordering Information 13 ...

Страница 3: ...e CSA certified for use in Class I Division 1 Groups B C and D and Class I Division 2 Groups A B C and D areas They are fitted with a sealed sampling cup with compression type 0 25 inch o d tubing fittings for easy integration into a vapor sample extraction system FEATURES Routine calibration not required Continuous self test automatically indicates a fault or fouled optics condition Performs well...

Страница 4: ...hane calibrated PIRVOL LT 95 8522 Figure 1 4 to 20 ma Current Loop Resistance Table 1 Current Loop Output Levels and Corresponding Status Indications Current Level Status 23 0 ma 100 by volume 20 0 ma 90 by volume 4 0 ma Zero gas level 0 by volume 2 2 ma Zero calibration in progress 2 0 ma Span calibration in progress 1 8 ma Calibration complete remove gas 1 6 ma Calibration fault 1 0 ma Fouled op...

Страница 5: ...h 5 watt walkie talkie keyed at 1 meter ENCLOSURE MATERIALS Copper free aluminum clear anodized enclosure Stainless Steel 316 electropolished enclosure SAMPLE DRAW CUP Material Aluminum Fittings Brass Tubing Size 1 4 inch O D MOUNTING Det Tronics junction box available in a tall cover with window or a short cover version is recommended for optimum ease of installation PIRVOL can be threaded into a...

Страница 6: ...s designated reference and the other active with different optical filters in front of the two sensors to make them selective to different infrared wavelengths The reference wavelength is unaffected by combustible gases while the active wavelength is absorbed by combustible gases The ratio of the active to the reference wavelength is computed within the PIRVOL to determine the concentration of gas...

Страница 7: ...PIRVOL it enters a Warmup mode for approximately one minute in which it performs diagnostic checks and allows the sensors to stabilize before beginning normal operation The current output during this period is 0 milliamperes At the end of the warmup period with no faults present the PIRVOL automatically enters the Normal operating mode If a fault is present after the warmup the current output will...

Страница 8: ...th the PIRVOL Tall Cover Model junction box cover includes a window See Figure 6 Short Cover Model junction box uses solid cover This junction box can also be used for detector separation See Figure 7 General Wiring Requirements NOTE The wiring procedures in this manual are intended to ensure proper functioning of the device under normal conditions However because of the many variations in wiring ...

Страница 9: ... 4 to 20 ma signal output Yellow lead Calibration input Green lead Chassis ground If the calibration wire yellow lead is not being used do not connect this wire to ground Trim excess length and insulate wire so no shorting can occur 95 8522 Figure 6 Tall PIRVOL Junction Box with Window Figure 7 Short PIRVOL Junction Box Figure 9 Typical PIRVOL Wiring with Det Tronics Junction Box DET TRONICS JUNCT...

Страница 10: ... the transmitter and then to the PIRVOL to ensure that the power requirements are met Mounting and Connecting Procedure for Detector Separation The PIRVOL junction box can be mounted to a wall or post or it can be suspended by the conduit if this does not result in excessive vibration The junction box should be electrically connected to earth ground 1 Lubricate the sensor threads with low vapor pr...

Страница 11: ...ng threads on the PIRVOL and associated junction box A suitable grease is listed under Spare Parts in the Ordering Information section of this manual It is recommended to keep spare IR modules See Spare Parts section for field replacement in the event of a malfunction 95 8522 Current Level Status Corrective Action 2 4 to 3 9 ma Negative Zero Indication NOTE This fault can be caused by the presence...

Страница 12: ...up from the front of the PIRVOL See Figure 12 2 Perform a visual inspection of the sample draw cup and associated plumbing and clean as required Also inspect the two O rings inside the sample draw cup and clean lubricate or replace as required 3 Loosen the two captive screws on top of the mirror assembly Figure 12 and remove the mirror assembly and hydrophobic screen from the electronics assembly ...

Страница 13: ...rocured Calibration Procedure To perform a zero calibration of the PIRVOL follow the sequence described in Table 3 NOTE The calibration sequence is initiated by momentarily connecting the calibration lead to the negative lead common of the power supply using either the Cal Magnet or an external switch If the Det Tronics junction box with magnetic Cal Switch is being used this is accomplished by ho...

Страница 14: ... packing material in addition to an anti static bag or aluminum backed cardboard as protection from electrostatic discharge Return all equipment transportation prepaid to the factory in Minneapolis Description Current LED Operator Action Normal operation no gas present 4 0 ma Off If the possibility of background gases exists purge the sensor with clean air to ensure accurate calibration Initiate c...

Страница 15: ...7128 001 Sample Draw Cup with O Rings and Fittings 007128 002 O Ring Kit UL 006297 003 Hydrophobic Screen 006680 001 Silicone Grease Assistance For assistance in ordering a system to meet the needs of a specific application contact Detector Electronics Corporation 6901 West 110th Street Minneapolis Minnesota 55438 USA Operator 952 941 5665 or 800 765 FIRE Customer Service 952 946 6491 Fax 952 829 ...

Страница 16: ... IR Combustible Gas Detector Eagle Quantum Premier Safety System Eagle Logic Solver Safety System Det Tronics the DET TRONICS logo Eagle Quantum Premier and Eclipse are registered trademarks or trademarks of Detector Electronics Corporation in the United States other countries or both Other company product or service names may be trademarks or service marks of others Copyright Detector Electronics...

Отзывы: