PART II: INSTALLATION
18
MOUNTING AND CONNECTING THE BURNER
Transport and storage
If the product must be stored, avoid humid and corrosive places. Observe the temperatures stated in the burner data table at the begin-
ning of this manual.
Handling the burner
The burner is designed to work positioned according to the picture below. For different installations, please contact the Technical
Department.
Fitting the burner to the boiler
To install the burner into the boiler, proceed as follows:
make a hole on the closing door of the combustion chamber as described on paragraph “Overall dimensions”)
place the burner to the boiler: lift it up and handle it according to the procedure described on paragraph “Handling the burner”;
place the 4 stud bolts (5), according to the burner’s drilling plate described on paragraph “Overall dimensions”;
fasten the 4 stud bolts;
place the ceramic fibre plait on the burner flange;
install the burner into the boiler;
fix the burner to the stud bolts, by means of the fixing nuts, according to the next picture.
After fitting the burner to the boiler, ensure that the gap between the blast tube and the refractory lining is sealed with appropriate insu-
lating material (ceramic fibre cord or refractory cement).
ATTENTION! The equipment must be installed in compliance with the regulations in force, following the manufac-
turer’s instructions, by qualified personnel. All handling operations must be carried out with appropriate
resources and qualified personnel
ATTENTION: Use intact and correctly dimensioned hoisting equipment, conforms to the local regulations and
health and safety regulations. Do not stand under lifted loads.
Packing
Burners are despatched in cardboard packages whose dimensions are:
1636mm x 1036mm x 1016mm (L x P x H).
Packing cases of this type are affected by humidity and are not suitable for stacking.
The following are placed in each packing case:
burner with detached gas train;
gasket or ceramic fibre plait (according to burner type) to be inserted between the burner
and the boiler;
(if provided) detection photoelement deatached from the burner
envelope containing this manual and other documents.
To get rid of the burner’s packing, follow the procedures laid down by current laws on disposal
of materials.
WARNING! The handling operations must be carried out by specialised and trained personnel. If these
operations are not carried out correctly, the residual risk for the burner to overturn and fall down still persists.
To move the burner, use means suitable to support its weight (see paragraph “Technical specifications”).
Note: the figure is indicative only.
PART II: INSTALLATION
H
P
L
SIDE UP
SIDE DOWN