C.I.B. UNIGAS
- M039135CG
14
spacer to move the burner backwards or to design a blast tube tha suites the utilisation (please, contact the manifacturer).
Installing the gas train
The following diagram shows the gas train components which are included in the delivery and those which must be fitted by the custo-
mer. The diagram complies with regulations in force.
Keys
1
Burner
2
Multibloc valves group: Multibloc DUNGS (2 gas gas pressure pressure governor)
3
Bellow joint
4
Manual cutoff valve
Once the train is installed, connect the gas valves group plug.
Fig. 3
Key
a) Heat output in kW
b) Lenght of the flame tube in meters
c) Flame tube firing intensity in MW/m
3
d) Combustion chamber diameter (m)
Fig. 3 - Firing intensity, diameter and lenght of the test flame tube as a function of the heat
input in kW.
ATTENTION:
BEFORE EXECUTING THE CONNECTIONS TO THE GAS PIPE NETWORK, BE SURE THAT THE
MANUAL CUTOFF VALVES ARE CLOSED. READ CAREFULLY THE “WARNINGS” CHAPTER AT THE BEGINNING
OF THIS MANUAL.
ATTENTION:
once the gas train is mounted according to the diagram, the gas proving test mus be performed, according to
the procedure set by the laws in force.
1
2
3
4
MANUFACTURER
INSTALLERINSTALLER