10
PK 1 | Version 1.03
Oparation
Step 1: Place the trolley on the track and follow the as-
sembly instructions supplied with the trolley (see
Fig. 2).
Step 2: Attach a suitable load chain to the vehicle.
Step 3: Lifting and lowering the track:
(Attention: Never change the height under load).
The height adjustment must be made by 2
people in order to carry out the adjustment on
both sides at the same time.
Fig. 5: Release clamping lever for height adjustment
Attention: Check that the locking bolts (fig. 4,
pin 1) are in the lower position on both sides of
the gantry crane.
Loosen the two clamping levers (fig. 3, 1 + 2)
on each side of the gantry crane.
Step 4: Lift the Rail (Fig. 4):
Fig. 6: Lift the Rail
Lift the suspension hooks (Fig. 4, 2) with the
locking bolts in the lower position simulta-
neously on both sides by pressing down the
two levers for height adjustment (Fig. 4, 3).
Fig. 7: Positions of the safety bolts
When the next position hole appears in the guide slot, in-
sert the second locking pin into the newly visible lower hole
- then as the lower locking pin - and slowly lower until it
supports the weight (Fig. 5). Repeat these procedures until
the desired height is reached. (13 holes are availa-
ble).Clamp the carriers by tightening the two clamping le-
vers (Fig. 3, 1 + 2). Loosen the two clamping levers (fig. 3,
1 + 2). Insert the locking bolt into the upper hole (Fig. 5,1).
Lift the carrying hook with the upper securing bolt (Fig. 5,
3). Lift the height adjustment lever slightly to loosen the
weight on the lower safety pin (Fig. 5, 2). Remove the lower
securing pin (Fig. 5, 2) and carefully insert the upper secu-
ring pin (Fig. 5, 1) into the lower hole. Repeat these proce-
dures until the desired height is reached. Clamp the car-
riers by tightening the two clamping levers (Fig. 3, 1 + 2).
The entire height adjustment procedure must be performed
simultaneously on both supports to ensure that the track re-
mains horizontal.
Step 5: Position gantry crane:Release the parking brakes,
roll the gantry crane to the desired position, and
then lock the parking brakes on the rollers again.
Secure the gantry crane additionally by fixing the
rollers with wedges against slipping or rolling away!
Step 6: Make sure that the load chain and the load hook
do not hang in a dangerous position.
Step 7: Insert the load hook into a suitable receptacle on the load
(tested load-receiving means: eg carrier, chain, belt, eyelet).
Step 8: First only lift the load until the load chain is tensio-
ned. Check the stability of the connections and the
vertical alignment of the load chain (no lateral
load!).
Step 9: Then lift the load to the desired height and drive
it to the desired position with the carriage. Care-
fully release the load there.
CAUTION!
Never move the gantry crane while it is under load!
CAUTION DANGER OF CRUSHING!