Montage & Cabling 

 

Figure 3

 

3.1

 

System arrangement 

The sensor electrodes must be manufactured as described in chapter "2.2 Sensor Electrodes". 

The following basic rules apply to the assembly of the system: 

●  Montage and adjustment should only be done by qualified person. 
●  The sensor electrodes should be installed in such a way that the measurement electrode stays 

as close as possible to the objects to be detected. This ensures safe switching behavior. 

●  The evaluation unit should be installed near the sensor electrodes. The sensor line (coaxial cable 

between the evaluation unit and sensor electrodes) should be limited to a maximum length of 100 
cm. 

●  The device may only be operated with the plastic cover closed! 

Before connecting the coaxial cable to the electrodes, check that: 

–  there is no short circuit between measurement electrode "A" and its opposite "B", 
–  there is no electrical connection between the electrodes and the mounting structure "C", 
–  there is no electrical connection to the machine ground. 

Содержание S-SW-8

Страница 1: ...manual adjustment switch SW2 2 to OFF 6 2 4 2 Sensitivity setting relay switching point 6 2 5 Technical Data 7 3 Montage Cabling 8 3 1 System arrangement 8 3 2 Electrical connections 9 4 Installation...

Страница 2: ...the sensitivity is set appropriately the presence of the new objects is detected A potential free contact relay turns ON OFF according to the IN OUT movement of objects over the sensing area the swit...

Страница 3: ...Connections Con nector Pin Connection X1 1 24 VAC DC Supply Voltage Both polarity accepted 2 3 PE Reference Potential Connected to the earth X2 1 C Relay common contact 2 NO Relay normally open contac...

Страница 4: ...of the evaluation unit via the shield of the coaxial cable Montage structure C The design of the mounting structure depends on the conditions at the installation place It must be made of conductive ma...

Страница 5: ...switch on point occupied and the switch off point free for the relay The sensor signal level for the switch ON point is stronger than the switch OFF point A larger hysteresis means that the switch ON...

Страница 6: ...ves the reference value of the system The sensor electrodes must be free when performing a new adjustment No objects or person may be near the sensor electrodes SW2 2 OFF Memory OFF After power ON the...

Страница 7: ...n 2 5 Technical Data Parameter Sim Condition min tip max Unit Supply Voltage UV AC DC 18 24 30 V Operation Power IV 18V UV 30V 3 W Environment Tempera ture TF In operation 15 20 55 C TL Storage 20 60...

Страница 8: ...ts to be detected This ensures safe switching behavior The evaluation unit should be installed near the sensor electrodes The sensor line coaxial cable between the evaluation unit and sensor electrode...

Страница 9: ...e 5 Connect the reference potential of the evaluation unit X1 3 direct to the earthed mounting struc ture 6 Connect the supply voltage 24VAC DC to the evaluation unit X1 1 X1 2 7 First operation By th...

Страница 10: ...timum sensitivity for the working object is set LED2 confirms the process by flashing briefly 2 Manual Relay OFF LED5 OFF Rotate the switch SW1 clock wise until the relay switches ON plus three more p...

Отзывы: