7 - USE AND OPERATION
7
-
Pag. 8/14
THIS MANUAL IS PROPERTY OF
-
ANY TOTAL OR PARTIAL REPRODUCTION IS STRICTLY FORBIDDEN
Cap.
FIG.34
7.7
LOADING THE MATERIAL
LOADING THE MATERIAL
Use nytril fibre gloves for protection against cuts and abrasions.
The mixture must have a plastic consistency (not too dry and not too wet).
Start the machine opening the air flow cock (FIG.35-REF.1-3): the pump starts to pump the slurry that was previously poured
into the hopper.
With the by-pass lever (FIG.37-REF.2) in the vertical position (hopper recirculation) check that the pump engages.
If this does not occur, switch the machine off, open the flow stand, remove the inspection cap of the flow valve (FIG.36-REF.1)
remove the rubber ball (FIG.36-REF.2) and pour the slurry into the valve body (FIG.36-REF.3).
Then re-position the ball and the inspection cap and finally close the stand and re-start.
Take the by-pass lever (FIG.27-REF.2) to the horizontal position: the machine starts to pump slurry into the piping.
3
2
1
2
3
1
FIG.35 FIG.36
Version with mixer (EMF version)
Activate the mixer by acting on the mixer switch (FIG.32-REF.3) and prepare the mixture.
Load the aggregates, the binder and water into the mixer.