site compliance

The site must be prepared by the customer or an agent who is fully conversant with the requirements of install-

ing ATM equipment. The responsibility for ensuring  that the site is prepared  in compliance with this document 

remains with the customer. 

For information and guidance only, a list is provided to outline the general matters for which the customer is re-

sponsible. This list is not intended to be comprehensive and in no way modifies, alters, or limits the responsibility 

of the customer for all aspects of site preparation. These procedures should be carried out prior to the arrival of 

the ATM.

1.  Location of the ATM and site preparation. Ensure access is not hindered by cabinet placement.

2.  Site wiring (power and communications).

3.  Location of any other equipment that may cause electrical, electromagnetic, or head induced interference.

4.  Installation of all communications cables, wall jacks, and other associated hardware.

5.  Installation of any necessary power distribution boxes, conduits, and grounds.

6.  Make any required building alterations to meet wiring and site requirements.

7.  Ensure all applicable codes, regulations, and laws are adhered to.

8.  Ensure environmental requirements of the unit are met.

9.  Install ATM terminal in accordance with ADA/DDA/CSA accessibility regulations for the state or country  of 

installation.

site preparation

Site Preparation Checklist

Select site and design floor plan.
Plan installation and accessory needs before starting. Ensure instal-

lation accessories are available.
Check floor plan and make necessary alterations.
Ensure all environmental conditions of the unit are met.
Check communication line requirements.
Install and test communications lines. 
Install and test all required electrical fixtures/power outlets.
Establish  contractor and vendor schedules.
Plan operator training exercises (optional).

1.  Temperature and humidity must fall within the following ranges for ARGO FT operation:

 

Temperature (Exterior)

 

-30°F to 0°F

 

0°F to 40°F

 

40°F to 122°F

Humidity (Interior, Non-Condensing)

 

10% - 20%

 

10% - 30%

 

20% - 80% (20% - 70% for polymer banknotes)

Temperature (Interior)

 

70°F to 80°F

 

60°F to 80°F

 

50°F to 104°F

Содержание atmgurus ARGO

Страница 1: ...red trademarks of Triton Systems of Delaware LLC The third party trademarks that may be identified herein are the trademark of their respective owners Triton disclaims any affiliation connection or as...

Страница 2: ...ranty Distributor s sole and exclusive remedy in the event of defect is expressly limited to the replacement or correction of such defective parts by manufacturer at its election and sole expense exce...

Страница 3: ...ensions thin wall 14 preferred service area 15 minimum service area business hours 16 minimum service area level 1 vault 17 cabinet footprint thin wall 18 cabinet footprint thick wall 19 unlock the el...

Страница 4: ...ation Act emv Europay Mastercard and Visa epp Encrypting pin pad fcc Federal Communications Commission fic Facility interface code iso International Organization of Standardization in Inches it Isolat...

Страница 5: ...the unit 1 What is the floor structure wood concrete etc Do you have anchors lag bolts and or screws to secure cabinet plinth 2 Is the unit a Level 1 vault or a business hours cabinet Will the floor s...

Страница 6: ...ny necessary power distribution boxes conduits and grounds 6 Make any required building alterations to meet wiring and site requirements 7 Ensure all applicable codes regulations and laws are adhered...

Страница 7: ...e duplex outlet and service panel ends of the line 3 The following telephone line requirements must be met Dedicated Line The telephone line servicing the ATM will not be a party line fax machine poin...

Страница 8: ...lips screwdriver 3 4 19mm socket 1 2 carbide tipped masonry drill bit 6 long Adjustable crescent or ratchet wrench 1 4 open ended or ratchet wrench Rotary hammer 7 16 box or socket wrench Torque wrenc...

Страница 9: ...same height and ATM is elevated with two 2 4 in Triton plinths totaling a plinth height of 4 3 4 in 122 mm Recommended Wall Opening Dimensions Fascia Trim Dimensions Height from Exterior Ground A Wid...

Страница 10: ...e same height and ATM is elevated with two 2 4 in Triton plinths totaling a plinth height of 4 3 4 in 122 mm Recommended Wall Opening Dimensions Fascia Trim Dimensions Height from Exterior Ground A Wi...

Страница 11: ...on Systems 11 customer access dimensions walk up only business hours and level 1 34 7 16 in 875 mm 43 3 16 in 1097 mm 36 in 914 mm 34 3 8 in 873 mm 27 7 16 in 696 mm 32 1 8 in 816 mm 70 15 7 1 4in 185...

Страница 12: ...on Systems 12 customer access dimensions drive up only business hours and level 1 27 7 16 in 696 mm 37 1 16 in 942 mm 33 1 4 in 844 mm 37 in 939 mm 38 5 8 in 981 mm 45 5 8 in 1159 mm 85 70 3 5 16 in 8...

Страница 13: ...d level 1 25 9 16 in 650 mm 22 7 16 in 570 mm 1 1 4 in 32 mm 59 1 4 in 1505 mm 2 1 16 in 52 mm 22 3 8 in 569 mm 36 7 8 in 936 mm 2 in 51 mm 11 3 4 in 299 mm 37 5 16 in 948 mm 38 9 16in 979 mm 38 15 16...

Страница 14: ...and level 1 25 9 16 in 650 mm 22 7 16 in 570 mm 1 1 4 in 32 mm 59 1 4 in 1505 mm 2 1 16 in 52 mm 22 3 8 in 569 mm 36 7 8 in 936 mm 2 in 51 mm 6 1 4 in 159 mm 31 13 16 in 808 mm 33 in 839 mm 33 7 16 i...

Страница 15: ...16 in 465 mm 22 9 16 in 573 mm 18 in 457 mm 17 in 432 mm 17 1 8 in 436 mm Tube Width L Safe Door Swing BH 180 Level 1 125 Tube Door Swing 172 Configuration BH and Level 1 L Thick Wall Walk Up Drive Up...

Страница 16: ...6 in 69 mm 2 1 16 in 52 mm 2 13 16 in 71 mm 5 7 16 in 138 mm 5 13 16 in 147 mm 19 15 16 in 507 mm L Safe Door Swing BH 105 Space Required To Remove Dispenser 17 1 8 in 436 mm Tube Width Tube Door Swin...

Страница 17: ...78 mm 2 1 2 in 63 mm 2 11 16 in 69 mm 2 11 16 in 69 mm 19 15 16 in 507 mm L Space Required To Remove Dispenser 17 1 8 in 436 mm Tube Width Tube Door Swing 90 Safe Door Swing BH 98 Note 10 inch thick...

Страница 18: ...Triton Systems 18 cabinet footprint thin wall drive up 14 1 8 in 359 mm 11 in 279 mm 15 3 16 in 386 mm 13 3 4 in 350 mm 4 1 2 in 114 mm Anchor Holes 1 in...

Страница 19: ...Triton Systems 19 cabinet footprint thick wall 10 in 254 mm 19 1 4 in 490 mm 15 3 16 in 386 mm 11 in 279 mm 14 1 8in 359 mm Anchor Holes 1 in...

Страница 20: ...is opened the door may be opened Open door by lifting up on the lever under the tab on the vault door The bolt will retract when door is opened on the swing bolt style lock Invalid code entry Lock wi...

Страница 21: ...dispenser is uninstalled or put into service For customers outside the US see Appendix B for alternate dispenser options 1 Unlock and open the top cabinet door Verify that the power switch on the powe...

Страница 22: ...e routing bracket on right side of dispenser 9 Using two people grasp the green handles located on each side of dispenser lift dispenser off rails and slide out of cabinet 10 Place dispenser in a safe...

Страница 23: ...ol panel trim 4 Once plinth is installed or if no plinth is required slide the unit forward into the wall opening so that tube protrudes from exterior wall Minor adjustments for raising leveling the u...

Страница 24: ...ube then rocking the trim toward tube until the four hooks on each side of trim fit into corresponding slots on tube 2 After hooks are inserted slide trim down firmly 3 Once trim is seated securely op...

Страница 25: ...ed flip light bracket down over ATM sign 8 With one person on the exterior and one person on the interior slide the unit back until control panel trim is flush with the outside wall 9 Make any final a...

Страница 26: ...hould be left clear to allow air to circulate at room temperature on the interior Caution Do not seal between bottom edge of control panel trim and exterior wall to allow water to drain 1 Using a wate...

Страница 27: ...of vault Ensure cables run over top of bracket so that cables are not pinched between bracket and vault Brackets will cover the ac cess hole that power and communication cables are routed through 4 Pl...

Страница 28: ...using an existing in house communications network Triton ATMs are equipped with an SSL secure socket layer option and loaded with public SSL certifi cates for secure communications Host processors may...

Страница 29: ...d turn the power switch on the power supply to the off O position 4 Remove blue tape from rear service panel mounting bracket The mounting bracket for the rear service panel is located in the upper ri...

Страница 30: ...a cable connectors are on the bottom side of the panel 7 Once rear service panel is securely mounted reinstall screw 8 Connect the data cable to the rear service panel Tighten two thumb screws to secu...

Страница 31: ...from the left side of receipt printer 3 Remove receipt paper roll and spindle from accessories 4 Place the paper roll on the spindle Ensure paper feeds from the top of the roll 5 Place the paper roll...

Страница 32: ...sert the edge of the paper into the printer take up slot The printer will automatically grip and pull receipt paper into the paper path 8 Perform a test print via Management Functions Diagnostics Prin...

Страница 33: ...rails so damage does not occur during dispenser installation 4 Disengage locking pin on left slide rail and pull slide rails out of cabinet until they reach fully extended posi tion 5 Using two peopl...

Страница 34: ...lide dispenser into the cabinet until the slide rail locking pin is engaged then close vault door 12 In the top cabinet place the power switch on the power supply to the on I position This completes t...

Страница 35: ...not cause harmful interference This device must accept any interference received including interference that may cause undesired operation Note This equipment has been tested and found to comply with...

Отзывы: